Reference no: EM131145831
Overhead
AJack Partnership manufactures jackhammers. AJack Partnership is looking for guidance in the variances of its standard cost system. It would like you to assist in understanding material price, material quantity, rate, efficiency, and overhead variances.
The standard cost card information for unit of product is below.
Standard cost card per unit of product
|
|
Direct materials: 4 pounds at $9.00 per pound of steel
|
$36.00
|
Direct labor: 2.0 direct labor hours at $20.00 per hour
|
40.00
|
Variable overhead: 100% of a direct labor hour at $10.00 per hour
|
20.00
|
Fixed overhead: 100% of a direct labor hour at $20.00 per hour
|
40.00
|
Standard cost per unit
|
$136.00
|
The following information is available in the year just finished:
• AJack Partnership manufactured 10,000 jackhammers during the year.
• The total purchases of steel in the year at a cost of $8.75 per pound were 45,000 pounds.
• All of the material was used to manufacture the 10,000 jackhammers.
• There was no beginning or ending inventory.
• The material was purchased on January 15, 20XX
• AJack Partnership incurred 21,000 direct labor hours at $19.50 per hour.
• During the year, one production order was issued on February 15 20XX, number 789, for 10,000 jackhammers.
• Actual variable overhead was $210,000.
• Actual fixed overhead was $405,000.
ASSIGNMENT:
1. Compute the variable overhead rate variance.
2. Compute the variable overhead efficiency variance.
3. Provide the accounting entry for the overhead rate and efficiency variances.
What type of tax rate structure does the us tax system apply
: What type of tax rate structure does the U.S. tax system apply? What are the individual tax forms, and what factors are used to determine which one to use? What is taxable income, and how is it determined?
|
The npv of the investment
: if we wanted the price after the offering to be $50 per share , and the NPV of the investment would be $.- Accounting dilution does not does occur in this case.
|
What would you estimate the scrap rate
: What would you estimate the scrap rate to be using a 6-month moving average? Using that scrap rate, what would be your material estimate for a new contract for the item when the material required for the finished product is $90,000?
|
Why is there unemployment in the economy
: Given your answer to part (a), why is there unemployment in the economy? (What would happen to real wages if the unemployment rate were equal to zero?)
|
Compute the variable overhead rate variance
: Compute the variable overhead rate variance. Compute the variable overhead efficiency variance. Provide the accounting entry for the overhead rate and efficiency variances.
|
Which of the following actions should you take
: Your maintenance chief has reported that a mechanic you hired from another regional airline told him that the other airline did a lot of "pencil maintenance." Which of the following actions should you take
|
Is decline in unemployment equal to increase in employment
: Compute the change in the number of unemployed from the first number in the table to the most recent month in the table. Do the same for the number of employed workers. Is the decline in unemployment equal to the increase in employment? Explain in..
|
Administrative issues impact external recruitment planning
: Explain how external influences, organizational issues, and administrative issues impact external recruitment planning• Analyze the advantages and disadvantages of using recruiters both from external and internal sources
|
Using hofstede conceptualizations of culture described
: Using Hofstede’s conceptualizations of culture described in your textbook, discuss an example of a “cultural conflict” you have observed or read about.
|