Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct

A - The third project takes 160 days

B - The fourth project takes 145.8 days

C - The fifth project takes 162 days

D - The eight project takes 131.2 days

E - None of them is correct

 

 

Reference no: EM13808687

Questions Cloud

The court held that lightle committed fraud : The court held that Lightle committed fraud by not telling the truth about the contract status of the house. Did he intend to deceive the buyer? Since Lightle was the representative of the sellers, the Leighs, why should he have any obligation to the..
Advantages and disadvantages of using the pert approach? : What would you consider as advantages and disadvantages of using the PERT approach?
Presenting this to a project team : Project Management:  Develop a 5-6 slide PowerPoint presentation. Explain the nature of project management, the role of the project manager, and the 3 factors that affect the success of a project.In the "notes" section of the slide write the commenta..
Create a total quality team : You are required to create a total quality team. When you complete your work, you are to present it to the board of directors for approval. Among the things you must consider: Who should make up the team? What size should the team be? From which depa..
A set large scale development projects : Assume a firm works on a set large scale development projects, in which the learning curve theory can be utilized. The first project takes 200 days and the second project takes 180 days. Which of the following statements is correct A - The third pro..
Describe an ethical dilemma : 4. Describe an ethical dilemma that a project team member might face while being part of an IT project. Discuss how the project manager could aid in avoiding or resolving such a dilemma. Discuss where this dilemma falls within the PMI and ACM codes. ..
What is the retailers effective cost of trade credit : A large retailer obtains merchandise under the credit terms of 3/20, net 40, but routinely takes 60 days to pay its bills. (Because the retailer is an important customer, suppliers allow the firm to stretch its credit terms.) What is the retailer's e..
What is counts unlevered beta : Counts accounting has a beta of 1.25. The tax rate is 35%, and Counts is financed with 45% debt. What is Counts' unlevered beta?
Currently bonds with a similar credit rating and maturity : Currently bonds with a similar credit rating and maturity as the firm's outstanding debt are selling to yield 8.32% while the borrowing firm’s corporate tax rate is 34%. The after tax cost of debt for the firm is ________% Common stock for a firm tha..

Reviews

Write a Review

Project Management Questions & Answers

  Annual holding costfredericks farm factory fff currently

annual holding costfredericks farm factory fff currently marintains an average inventory valued at 3400000. the company

  Create a wbs for the scope of the project

Analyze the various activities required for this project and provide an estimate of duration for each activity based on the number of resources available for the project. Include assumptions and basis for each estimate

  Using the stratified sampling formula

Using the stratified sampling formula, estimate the proportion of the students who graduated from four year colleges in Kansas that carried student debt upon graduation.

  Your company has an average annual inventory

Your company has an average annual inventory of $70 million. Its annual cost of goods sold (COGS) is $560 million. Order costs are $195 per order

  Show the project proposal outline and summary

List the desired outputs from the project. Specify the performance criteria for the project and a statement of work (SOW) must be developed to define what is and what is not included in the project.

  Part of a project to be scheduled using cpm

What is the critical path and how many weeks will lit take to complete be project

  Risk assessment in project documentation

As a project manager, the risk assessment is one of the most important pieces of project documentation.

  Projects that are part of the functional organization must

projects that are part of the functional organization must compete with the organization for recognition and resources.

  Computing expected return on project using capm

What is the expected return on the project using CAPM?

  Show the importance of communication in business- dsecribe

show the importance of communication in business- dsecribe the importance of communication in business- explain the

  Project management-budget vs actual costs

Explain what might a seasoned project manager who understands earned value recognize as not-good-news about the situation and its impact on the project

  Questionyour company wants to expand special

questionyour company wants to expand special leadership-oriented resources for project managers in its new project

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd