Q.What do you mean by Slip Siding?
If the Station yard is in a gradient steeper than 1 in 260 or there is a continuous falling gradient away from the station there is a possibility of vehicles standing in the yard entering or escaping into the block section and cause accidents to prevent such escaping of vehicles into the block section slip siding are provided.
At a station where there is a gradient 1 in 100 falling away from the station within 45 meters beyond the outer most points at either end a slip siding should be provided.
As per the schedule of dimensions no station yard should be constructed nor should any siding join a passenger line on a steeper grade than 1 in 260 except where it is unavoidable and then only with the previous sanction of the railway board obtained through the commissioner of Railway safety when a slip siding is made sufficient prevent accident.
I need technical assistance. The project is incomplete. I need someone to proofread it. Do you have someone who know Plaxis, Slope/W and Flac?. Can you arrange a case study for Geo
procedure of drawing free body diagram
neea BM & SF CALCULATIONS & DWNGS
Determine the principle of Darcy's law for laminar flow of water through saturated soil. Illustrate that the coefficient of permeability has the dimension of velocity. The d
Q. Explain about Bentonite slurry and polymeric slurry? For the construction of diaphragm walls, bentonite slurry is generally used to form a filter cake on walls of trenches t
Ask queexplain about the essential parts of transisit ordinate or vernier theodolitestion #Minimum 100 words accepted#
Sir, What is the dosage limit of densifier for SFRC concrete
what are the necessary data required for foundation recommendation other than SPT value ? why can''t we go for SPT value alone?
parabola by offset method
Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd