Q. What do you mean by GGBS – cement replacement?

From structural point of view GGBS replacement enhances higher durability, lower heat of hydration and higher resistance to sulphate and chloride attack when compared with normal ordinary concrete. Conversely it also contributes to environmental protection since it minimizes use of cement throughout the production of concrete. 

Though it is identified that there are still some hindrances which prevent the prevalence of its usage in local market. Theoretically speaking GGBS concrete suffers from lower rate of strength development that is highly sensitive to curing conditions. In this connection certain site measures have to be introduced to construction industry to ensure better quality of curing process in order to secure high quality of GGBS concrete. Along with designers have to be cautious of the potential bleeding problem of GGBS concrete.

Another main difficulty of extensive use of GGBS concrete lies in the little source of supply of GGBS. As Hong Kong isn't a major producer of steel and GGBS as a by-product of steel has to be imported overseas and this introduces higher material cost because of transportation and supply of GGBS is unsteady andunstable.


Related Discussions:- What do you mean by ggbs – cement replacement

Baur leonhardt system, What is the special feature of this system rather th...

What is the special feature of this system rather than other?? What do you mean by principal of looping system?

Write short note on stock verification, Q. Write short note on Stock Verifi...

Q. Write short note on Stock Verification? It is desirable that there should be a frequent reconciliation of the balances as shown in the numerical ledgers kept by the subordin

Environment engineering assignment, Estimate the ground level NO concentrat...

Estimate the ground level NO concentration: a. Directly downwind at a distance of 2 km b. At the point downwind where NO is maximum c. At a point located 2 km downwind and 0.1 km

Project management, planking and strutting for shallow excavation

planking and strutting for shallow excavation

Fore bearing, find out the interior angleS with diagrame LINE AB, BC, CD, D...

find out the interior angleS with diagrame LINE AB, BC, CD, DE, EA Fore bearing 60''30" , 122'' , 46'' , 205''30" , 300''

Optimum moisture content to grab maximum density, Question For compacti...

Question For compaction of free-draining sands or gravels, what is optimum moisture content to grab maximum density ? Answer Compaction curve of dirty materials is com

Surveying, closed traverse ABCDE form a regular polygon with fore bearing o...

closed traverse ABCDE form a regular polygon with fore bearing of line is 35 find the bearing of other lines

Hazard, • A potential source of harm - Mechanical hazard - Electrical...

• A potential source of harm - Mechanical hazard - Electrical hazard - Cutting hazard - Toxic hazard - Fire hazard - Explosion hazard

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd