Wet mix macadam - road pavements, Civil Engineering

Wet Mix Macadam:

For heavily trafficked highways, the granular bases are constructed using Wet Mix Macadam (WMM). The WMM is a specification in which well graded aggregate is mixed with water in a mixer and the mix is laid by a paver and rolled by a roller. Two gradings are used, one with graded aggregates below 53 mm (40 mm nominal size) and the other with aggregates below 26.50 mm (25 mm nominal size). The advantages of WMM over WBM are:

(a) The stone aggregates are well graded and hence a greater interlock results.

(b) Since it is laid by a paver, the resultant surface is even.

(c) Since excess water is avoided, the sub-grade does not get saturated with water and lose its strength.

Posted Date: 1/22/2013 4:38:19 AM | Location : United States





I want W M M mixing gradation

Posted by gajendra singh chauhan | Posted Date: 7/9/2013 1:31:42 AM
I want W M M mixing gradation

Posted by gajendra singh chauhan | Posted Date: 7/9/2013 1:32:38 AM


Related Discussions:- Wet mix macadam - road pavements, Assignment Help, Ask Question on Wet mix macadam - road pavements, Get Answer, Expert's Help, Wet mix macadam - road pavements Discussions

Write discussion on Wet mix macadam - road pavements
Your posts are moderated
Related Questions

Question Have air test or water tests be selected to test leakage of constructed gravity pipelines ? Answer For gravity pipes, air tests are carried out after completi

free body diagram of a walk bridge

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

Ask questa) In an unloaded propped cantilever, the propped end sinks vertically relative to the fixed end by an amount ? due to poor construction of the foundation of the prop. Wha


A contractor is bidding a construction project that will take 12 months to complete. The terms of the bid provide that the owner will pay the Contractor one lump sum at the end of

Thermocouples are utilized for the measurement of what temperature? Answer: It is utilized for the measurement of temperature.

Project Management: This unit starts with the general definition of Project management. Several phases involved in project management are also desribed. Further, the technique

Q. Replacement of loose rivets? i) Slight slackness of rivet does not cause loss of rivet strength. ii) Renewal of slack rivets should be done only when the slack rivets are