Transportation issues, Civil Engineering

"We have one other pressing challenge that you could review for us," Alistair Wu says. "As you know, the Shanghai plant was our first facility in China, but we also have two other production plants, at Hangzhou and Fuzhou. We call them the Shuzworld H and Shuzworld F."

"One of our major lines of women's shoes is produced at all three plants. In turn, the shoes are sent to Shuzworld's three central warehouses for further distribution to regional warehouses and then to the stand-alone retail and mall stores."

Wu reaches into his elegant leather briefcase and produces two charts, which he hands to you.

"This first chart shows our monthly production capacity for these shoes at each of our factories and our monthly requirements to meet demand at each of our warehouses," he explains. "We are producing at normal capacity at all three factories in order to meet our current demand."

Factory

Capacity

Warehouse

Requirements

Shanghai

1300

1

2500

Shuzworld H

2300

2

1500

Shuzworld F

2200

3

1800

Totals

5800

 

5800

He asks you to look at the next chart. "Here you can see what it costs us to ship on a per unit basis. For example, our most expensive route is to ship from Shuzworld F to Warehouse 3 and costs $6 per shipping unit."

To/From

Warehouse 1

Warehouse 2

Warehouse 3

Shanghai

$4

$3

$3

Shuzworld H

$3

$4

$2

Shuzworld F

$2

$4

$6

"We've decided to increase production at Shanghai from 1,300 units to 2,800 units," Wu continues. "There's no increase in demand right now, by the way, but this will enable us to meet the growth we expect in the near future. Meanwhile we will have some flexibility in case we have a problem at one of the factories. This move may also mean we can change our transportation schedule in the event that turns out to be advantageous. We want to know what the lowest possible monthly transportation cost can be and what shipping plan we should adopt to achieve that. Can you help us with this?"

Task:

A. Develop a distribution pattern that meets availability and demand constraints and minimizes total shipping costs for Shuzworld, utilizing the appropriate decision analysis tool.

Posted Date: 2/20/2013 2:40:01 AM | Location : United States







Related Discussions:- Transportation issues, Assignment Help, Ask Question on Transportation issues, Get Answer, Expert's Help, Transportation issues Discussions

Write discussion on Transportation issues
Your posts are moderated
Related Questions
Explain Designation of bearings. Calculate included angle from bearings

The oven-dry weight of a pat of clay is 1.17 N and the weight of mercury displaced by it is 0.855 N. suppose the specific gravity of solids as 2.71, verify the shrinkage limit and

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

For IRC Class AA loading in existing industrial areas, what is load (kN/m) has to applied base don the wheel loads. especially raft foundation & roads are at same level.

A moist soil sample compacted into a mould of 1000 cm 3 capacity and weight 35 N, weighs 53.5 N with the mould. A representative sample of soil taken from it has an initial weight

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Q. Explain Forty-five degree spread rule for driven piles ? For driven piles the length of piles driven into the ground is generally based on dynamic driving formula such as Hi

Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of