Line Balancing, Operation Management

#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..
Posted Date: 2/6/2013 3:12:12 AM | Location : USA





Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)
Posted by Daina | Posted Date: 2/12/2013 7:08:07 AM
Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..
Posted by Diana | Posted Date: 2/12/2013 7:09:42 AM


Related Discussions:- Line Balancing, Assignment Help, Ask Question on Line Balancing, Get Answer, Expert's Help, Line Balancing Discussions

Write discussion on Line Balancing
Your posts are moderated
Related Questions
program to find optimal sequence, total elapsed time and total idle time in 6 jobs and 3 machines

Complete a net material requirements schedule for: a) All items (10 schedules in all), assuming the requirement for each BOM item is 1. b) All 10 items, assum

1. Identify products which you would expect to be produced by each of the following configurations: project, job shop, and batch and continuous. Answer: Many possible answers:

Principle of Scheduling First Principle optimum Task Size : scheduling tens to achieve its maximum efficient task sizes are small and all tasks are of the same order of magnit

Identify and discuss the four distinguishing characteristics of a mature (well-functioning) group. Give an example of a mature group you have participated in and the application of

Respondeat superior is the theoretical basis for holding companies criminally liable for actions of their employees. Companies oftentimes have little defense against prosecution. C

An assembly line with a number of tasks is to be balanced. The sum of the task times is 100 minutes. The line will operate for 7 hours per day. What is the minimum number of wor

Consider the various roles members have to perform for a team to be effective. Which roles would play to your strengths and which to your weaknesses?

State how production standards place managements and unions at odds against each other. Why do some unions prefer the right to strike in this matter while others prefer arbitration

Please discuss different roles people play in work groups? Please share the role you predominantly played in project or work groups. Make this a very short answer