Line Balancing, Operation Management

#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..
Posted Date: 2/6/2013 3:12:12 AM | Location : USA





Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)
Posted by Daina | Posted Date: 2/12/2013 7:08:07 AM
Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..
Posted by Diana | Posted Date: 2/12/2013 7:09:42 AM


Related Discussions:- Line Balancing, Assignment Help, Ask Question on Line Balancing, Get Answer, Expert's Help, Line Balancing Discussions

Write discussion on Line Balancing
Your posts are moderated
Related Questions
Klein Industries manufactures three air compressors: small, medium, and large, which have unit profits of $20.50, $34, and $42 respectively. The monthly projected sales of small ar

Complete the Leadership in Action Ikea case on page 142-143 in your textbook on pernille spiers-lopez assembles a winning team at ikea .Answering the case questions involves ident

The following marketing phenomenon occurs when there exists within two city blocks the following hamburger outlets: McDonald's, Burger King, Sonic, and Wendys.

Over the past year, Meredith and Smunt Manufacturing had annual sales of 10,000 portable water pumps. The average quarterly sales for the past 5 years have averaged: Spring 4,00

The local lottery sets up a game wherein a player has a chance of collecting $800. The player must choose a 3-digit number and if it matches the lottery number, the player recei

Prepare Paul Jordan''s report to John Smithers using regression analysis. Provide a summary of the cell phone industry outlook as part of Paul''s response.n..

What are the characteristics of just in time philosophy? Characteristics of JIT philosophy: a. Closer relations along with suppliers maintained b. Smaller and extra fr

Describe the role of purchasing in contributing to the profitability of the enterprise

Describe FedEx manufacturing process and scheduling approach

Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration. Activities Precedes Duration Start a,b,c - a d 5 d f 6