Line Balancing, Operation Management

#What do you understand by “line balancing”? What happens if balance doesn’t exist?uestion..
Posted Date: 2/6/2013 3:12:12 AM | Location : USA





Line Balancing
- Line: an assembly line composed of various work stations, at which particular operations are performed.

- To work efficiently, with no work pile-ups between stations, the line must be balanced, for example work must get through each workstation in roughly similar amount of time.
Goals:
1. To meet production goals,
2. Maximize output.

General Approaches to Line Balancing Technique
1. Estimating number of operators for a specific number of stations,
2. Work element sharing: grouping “activities” each work elements into “stations” or jobs performed by a single person (occasionally multiple people work in concert at a single station or machine)
Posted by Daina | Posted Date: 2/12/2013 7:08:07 AM
Write your Aim – It only applies to assembly lines. It aims at minimizing the idle time along the line by dividing work equally among members. Tasks are grouped in such a way that they have equal time requirement.

When is line Balancing is Done

· When the line is initially set-up

· When the changes are made in process / desired output rate

Difficulty associated with LB – Not feasible to combine certain activities

Necessity of line balancing – In absence of line balancing, it might create morale problem for workers at slower station who work continuously

(Draw Precedence Diagram)

Cycle Time = Longest time at the any of the work element OR (Operating Time / Desired Output Rate)

CT = 1 min

(In Question, it may be given as 480 units per 8-hour day, Hence CT = 8*60 min per day / 480 units per day = 1 minute per cycle)

Theoretical Minimum number of workstations, Nmin = Sum of time at all WS / CT = (0.1+1.0+0.7+0.5+0.2) / 1.0 = 2.5 = 3 Workstations

Rules in Assigning task

1. Choose new WS if

a. All preceding tasks are completed

b. Task Time is less than or equal to Time Remaining

2. Always first assign the task with greatest task time to a workstation, in case there is a choice between work elements. In case task time is same, choose the element having greatest number of followers.

3. For every new WS, always start with cycle time

WS


Time Remaining


Eligible


Assign Task


Revised Time remaining


WS Idle Time

1


1.0


A,C


C(0.7)


0.3 (1.0-0.7)




0.3


A


A(0.1)


0.2


0.2

2


1.0


B


B(1.0)


0


0

3


1.0


D


D(0.5)


0.5




0.5


E


E(0.2)


0.3


0.3

Total Idle time = 0.2 + 0.3 = 0.5 minutes

Balance Delay in % (% of idle time on assembly line) = Total idle time * 100/ (Actual No of WS * Cycle Time)

=0.5*100/(3*1) = 16.7%

Line efficiency = 100% - Balance delay% = 83.3%

Other considerations in line-balancing

1. Technical considerations –

a. Skill requirement of different tasks - If the skill requirements of tasks are quite different, it may not be feasible to place the tasks in the same workstation

b. Incompatible tasks - If the tasks themselves are incompatible (example – Use of fire and flammable liquids), it may not be feasible even to place them in stations that are near to each other

2. Variable tasks by human –

a. Reasons for variation are Fatigue, boredom and failure to concentrate on the task at hand.

b. Absenteeism can also affect the balance

Other approaches to achieve smooth flow of production

1. Make parallel workstations – They increase the workflow and provide flexibility

2. Cross-train workers / Dynamic line balancing – It helps workers perform more than 1 task. In case they are idle, they can assist other workers who are temporarily over-burdened

3. Mixed model line - Design a line to handle more than 1 product on the same line. The different products are similar in many ways and hence, the process applied on them is also samemessage here..
Posted by Diana | Posted Date: 2/12/2013 7:09:42 AM


Related Discussions:- Line Balancing, Assignment Help, Ask Question on Line Balancing, Get Answer, Expert's Help, Line Balancing Discussions

Write discussion on Line Balancing
Your posts are moderated
Related Questions
Given the following data for Albert's fabricating production area: Fixed costs for one shift = $60,000 Unit variable cost = $7 Selling price = $12 Number of machines = 5 Number of

Perfect Face Cream ran a commercial to showcase its new Wrinkle-Free Face Cream. The commercial showed an older woman with severe wrinkles followed by images of that same woman aft

Create a research paper that discusses how one company (of your choice) illustrates social responsibility in its environment. Discuss what leadership does to promote social resp

I have a take home exam that I need to be solved 100 % correct , please . I need it within 23 hours EXACTLY from now please . Thank you so much and I am really looking forward to s

Activity Sampling - Process Design This is a method of finding the percentage occurrence of a certain activity by statistical sampling and random observation. It is used when

John Barks owns Barks Computer Screens Inc. and wants to identify the supply and demand for screens in his market. The company can produce large screens called Wides or small scree

Johnson Plastics makes and sells, among many other things, specialty plastic display cases for retail stores. Johnsons expected demand for the display cases is 1,000 units, and ave

Discuss the importance of influence. How you would attempt to apply it to convince your team to work an extra day per week to earn time off later. Analyze how you would influence y

Suppose a new hospital is to be built to provide medical and healthcare service to 5 towns coordinate (5,6), (1,3), (13,7),(11,2) and (8,1) on map, the transportation network is re

How do Loews' training programs relate to the company's business strategy?