The hotel refurbishment project, Project Management

Assignment Help:

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this sort of project). The timescale is not flexible as the hotel requirement to re-open to host the wedding of a very famous and influential music star.  In order to meet this deadline the project has no contingency.

B has been assigned as project manager and has focused on selecting the project team which has meant that no full plan has yet been produced.  When one of the project team members asked about the tools and techniques to be used on the project, B seemed unsure about which ones would be most beneficial and suggested that he was going to rely on project management software.  The project team is concerned about the lack of control on the project as there appear to be no project milestones.

It has been brought to B's attention that the hotel would like to add additional activities to the original project specification and requires a meeting to discuss the implications of the changes to the overall project progression.  B has asked about the project initiation document which he feels should form the basis for the discussion of the changes.  B has been told that the 'brief document' compiled by the hotel is the only document available.

Explain the problems that are threatening the success of the hotel refurbishment project and the ways in which B can minimise the threats identified

 

According to the scenario, there are a number of problems evident in the progress of the hotel refurbishment project.

Unrealistic deadlines

There appears to be pressure from the hotel to get the project finished rapidly with strict deadlines. The project is already behind schedule and there is no contingency in the project plan. B will require to look critically at the project deadlines. The time schedule will require to be revised. The critical activities need to be identified and B requires to make sure that they do not slip.

Resource estimates unrealistic

Core project staff that are significant to the delivery of the hotel project are being permitted to work on other projects. A critical issue in project planning is resource management. B will require to ensure that the hotel project has the correct level of manpower in the right place at the right time in the right quantities. B could use a resource histogram to provide a visual display of the usage and availability of resources over the project's life.

No detailed project plan

A key problem is the absence of a detailed project plan and specification. The hotel project is likely to contain a number of difficult tasks. One of the most important stages of project management is the explanation of the project objective and the breakdown of work into a comprehensive list of activities.

 


Related Discussions:- The hotel refurbishment project

Assessing Infrastructure Project-Related Risks, The Three Gorges Dam is pot...

The Three Gorges Dam is potentially one of the largest, if not the largest infrastructure projects completed in the 21st century. Clearly, there were a number of key risks that the

Addressing high nurse turnover at Bronson methodist hospital, identify purp...

identify purpose of case study , general information about hospital, identified problem and proposed solution

What are the causes of poor industrial relations, What are the Causes of Po...

What are the Causes of Poor Industrial Relations? Purposes of Poor Industrial Relations situation for good IR are as follows: a. Inadequate fixation of wages and wage struct

Real life project, Real life project make as a project manager do it critic...

Real life project make as a project manager do it critical evolution 3000 words

Evaluating the domain model, o Is the domain model a complete representatio...

o Is the domain model a complete representation of the relevant objects in the problem domain? o Are associations between problem domain objects captured? o Are specializatio

Project management requires three important activities, Question (a) Pr...

Question (a) Project Management requires three important activities, namely planning, estimation and scheduling. Discuss the differences between them. (b) Scheduling of proj

Different steps in an environmental impact assessment, Question 1: (a) ...

Question 1: (a) Distinguish between Life Cycle Assessment (LCA) and Environmental Management System (EMS) and outline the benefits of implementing an Environmental Management

Explain about the term cost-benefit analyses, Explain about the term cost/b...

Explain about the term cost/benefit analyses. Cost/benefit analyse: Cost/benefit analysis is the procedure of knowing, and as far as probable quantifying, the costs of res

Plan, Plan A plan is a blueprint or framework used to describe how an o...

Plan A plan is a blueprint or framework used to describe how an organization expects to achieve its goals. Planning is the process of developing plans or determining how best t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd