The economic cost of a project, Business Economics

Advanced Technology, Inc., (ATI) is evaluating a contract proposal calling for it to build and test bearings using a newly patented surface configuration. ATI would receive $1.4 million for the work. ATI's management believes that the bearings can be built and tested using existing facilities, with the exception of one piece of test equipment that can be rented at a cost of
$45,000. If the contract is accepted, 8000 hours of direct labor will be required. ATI calculates these labor costs at $110 per hour. This labor cost is derived by adding a 20-percent fixed overhead charge to actual direct labor costs, plus a 100-percent charge for the firm's required profit margin. The overhead and profit charges are the amounts that management believes
can be earned under normal conditions. Materials and supplies costing $250,000 will be purchased for the project, and 1,000 pounds of a specialty steel currently in inventory will be used. This steel cost $20,000 when purchased, and ATI estimates the cost of carrying the inventory since purchase at about 20 percent of initial cost. The steel has a current market value
of $18,000. Finally, management has determined that resources are currently fully employed, and acceptance of this job will require turning away other available business.

Accounting's cost projection for the bearing test job is as follows:
1. Direct labor cost
(8,000 hours @ $50 per hour) $400,000
2. Direct materials:
Purchased materials $250,000
Inventoried steel 24,000 274,000
=======
Total direct labor & materials 674,000
3. Equipment rental 45,000
4. Overhead (20 percent of direct labor) 80,000
5. Required profit margin
(100 percent of direct labor) 400,000
===========
Total project cost ' $1,199,000

Note: As pointed out above, percentages of direct labor are used as a means of estimating the contribution a job makes to overhead and profit under "normal" conditions. Remember these are financial accounting numbers. For example, numbers 4. and 5. above say little about "overhead" and "profit," since the 120% that is "typically" earned by a job with 8000 hours of direct labor, has been allocated to profit and overhead using some accounting rule. This means only that the total contribution to ATI of a job utilizing 8000 hours of direct labor is normally about 120% of direct labor charges billed.

a) Estimate ATI's economic (relevant) cost of accepting the contract.
b) How would an assumption that the economy was in a recession and that ATI didn't have enough business to keep its resources fully employed affect the relevant costs for this problem?

Be specific and re-estimate the costs of the job.
class notes and problems
economics 401
professor john m heineke

c) In parts a) and b) what are the economic profits associated with accepting the contract? What do these numbers mean?

Review: There are additional costs to consider when ATI is operating at capacity which are not relevant when there is excess capacity. A profit maximizing decision requires that the costs of the proposed contract be correctly calculated. There are two problematical types of costs here, (i) sunk costs which do not impact the return from the contract if it is accepted--in general the relevant costs associated with any project are those which change because the contract is taken-- and (ii) returns given up if the contract is accepted. Any returns that would have been earned, but will not be if the contract is accepted, are costs of accepting the contract. Therefore, whether the current operation has excess capacity or is at capacity is an important consideration.

Posted Date: 2/20/2013 4:25:38 AM | Location : United States







Related Discussions:- The economic cost of a project, Assignment Help, Ask Question on The economic cost of a project, Get Answer, Expert's Help, The economic cost of a project Discussions

Write discussion on The economic cost of a project
Your posts are moderated
Related Questions
This is concerned with any one of the following forms. controlling the supply of money controlling interest rates Rationing the amount of credit granted by banks

Is the Washington Consensus actually a consensus? The Washington agreement thinking dominates development thinking in the developed world but is challenged through less develo

Report the average and standard deviation of monthly return for your corporation and the S&P 500 on the spreadsheet.  Use the spreadsheet functions to calculate these: =AVERAGE(dat

Assume Mr. Robinson deposits pounds 600 in currency at a bank. Later that day Ms. Volker borrows pounds 1200 from the similar bank. The money supply will have enhanced by pounds 60

QUESTION ICT tools are deemed to present considerable opportunities to support a nations' sustainable development. The potential of e-Government in developing countries however

Consider another company, Lateco, which has just received its fifth round of investment.  These rounds have been: Series A: CP ($5M FV) or converts to 5M shares of common. Se

How does economic system influence the development process? The development experience of free market or capitalist and command as socialist/communist countries is extremely d

What is the fixed cost


Define the using influences of contract staff for IS project. Use of contract staff: Such are frequently an unknown quantity.  It is reasonable to assume that people who