Termination of contract and conditions for termination, Other Management

Termination of Contract and Conditions for Termination

One  event  which can arise in contract  performance management  is an extreme non-performance by either contracting parties which may necessitate or lead to termination of the contract.

Termination of contracts can be partial termination or entire contract termination. Cancellation of a portion of work is called partial termination while entire contract means an indivisible contract i.e. a contract in which the obligations of the two parties are interdependent, and consequently non fulfilment of significant obligations by one party makes it very difficult or impossible for the other party to continue with the contract.

Contracts invariably have a termination clause incorporated. This clause ensures that either or both parties have the right to terminate the contract under   certain   circumstances.   The   termination   clause   describes   the following:

  • Breach of contract events that trigger the right to terminate the contract.
  • Methods of giving notice of the exercise of the termination right.
  • Whether the breaching party must be given an opportunity to cure the breach before the other party can terminate the contract.

We will briefly discuss conditions in which a contract can be terminated as under:

  • Natural course of events: This is a trivial condition wherein the contract work has been completed, entire contract performance has been met, final acceptance has taken place,  the work  has been  paid  for,  and contract closure has taken place.
  • Breach of contract: A breach of contract takes place when a party fails to deliver on their contractual promises by failing to perform their obligations completely.
  • Mutual agreement: Contracts may be terminated by mutual agreement where the contract itself provides for the event (for instance upon 3 months notice); by the parties conduct; or where the parties enter into a separate agreement to terminate the earlier agreement (for example, a compromise agreement where there has been a dispute in respect to the earlier agreement).
  • Frustration: Frustration is a basis upon which parties may be excused from their obligations to perform as a result of events arising after the contract has been entered.
  • Termination for convenience: Many construction contracts also include a clause that allows the owner to terminate the contractor?s remaining work on the project at the owner?s convenience. Such a termination is not due to any fault on the part of the contractor.

Termination for convenience clauses are intended to provide the owner with the option to terminate the remaining balance of the contract for work for a reason other than the contractor?s default - for example, owner being unable to obtain additional financing to complete the work.

In addition to terminating the contract for cause or convenience, an owner can also delete all or a portion of the balance of the remaining scope of work. Should the owner make such a deletion at any time before or during performance of the contract, the contractor must review the contract to determine what his or her rights and obligations may be.

If the contract is terminated for convenience, the contractor will not earn the profit that was anticipated when the contract was executed. If the contract is terminated, the amount paid to the contractor may not recapture the contractor?s home office overhead that was allocated to the contract. While on the face of it, this may appear unfair to the contractor, in every contract there is an implied covenant of good faith and fair dealing. 

Posted Date: 9/28/2012 2:49:51 AM | Location : United States







Related Discussions:- Termination of contract and conditions for termination, Assignment Help, Ask Question on Termination of contract and conditions for termination, Get Answer, Expert's Help, Termination of contract and conditions for termination Discussions

Write discussion on Termination of contract and conditions for termination
Your posts are moderated
Related Questions
Use of the library: The researcher plans  to  concentrate the efforts on identifying information on  a specific topic. If you  are unfamiliar with a particular library get acquain

Classification Scheme: A scheme of classification is but a tool in the hands of the library to organise subjects and to serve them out in an efficient way. Therefore, it is ne

Dealer Library Plan (DLP): Under this plan, as agreement is reached between the library and the publishers or a group of publishers whereby the publishers send books as soon a

List out the secondary sources of information while pursuing market research

Explain the use of Hani Raafat risk calculator as a semi quantitative tool for assessment of risk

Overview of Procurement Management   Let us start our discussion with an overview of project procurement management. Procurement management is an important knowledge area in pro

Telecommunication Technologies: Telecommunication today involves microprocessors, digitization of information (audio, video and text) and its transmission across communication

#question. I want detailed information about entrepreneurship.


Copying Equipment -LIBRARY EQUIPMENT -LIBRARY MANAGEMENT Multiple copies of documents, for various purposes, are often needed in a library. Hence it is  necessary to provide s