Surface dressing - road pavements, Civil Engineering

Surface Dressing:

Surface dressing is an application of a thin film of bituminous binder followed by a coat of aggregates of single size, rolled into position. Surface dressing is done in one course (single coat) or two courses (two coats). Normally, the first coat is the heavier of the two. The second coat, which is lighter, is applied after the binder in the first coat works up around the cover aggregates, a process which takes up about 3-4 weeks. The quantity of binder and aggregates is as given in Table 5. The binder is a penetration grade bitumen 80/100 heated to 163-175oC or a cold application emulsion.

Table : Binder and Aggregates for Surface Dressing (Per 10 m2)

1719_Surface Dressing.png

The construction consists of spraying the binder by means of a mechanical sprayer, spreading the aggregates manually or by a mechanical spreader, and rolling the aggregates to a firm position. Rolling should proceed from the edges to the centre. Traffic is disallowed for the first 24 hours so that the binder hardens.

Posted Date: 1/22/2013 4:42:38 AM | Location : United States







Related Discussions:- Surface dressing - road pavements, Assignment Help, Ask Question on Surface dressing - road pavements, Get Answer, Expert's Help, Surface dressing - road pavements Discussions

Write discussion on Surface dressing - road pavements
Your posts are moderated
Related Questions
Maintenance of bituminous roads

Atomic weight of an atom is equal to? Answer: sum of the number of protons and neutrons.


According to National Building Code (Sp:7 1970), the differential settlement shall be kept within the limits to which the superstructure can accommodate itself without harmful dist

Example for Beam Flexure Design Select the lightest W section for the simply supported beam shown below.  The beam length is 12ft.  The nominal loading is: w d = 4.0 kip/ft (i

shrinkage factor in plans

what is the design of syphon

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish


Q. What are the causes of settlement? The various causes of settlement are: 1) increasing load on the surrounding soil deposit, 2) excavation, 3) lowering of water tab