Rolling - binder, Civil Engineering

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.

Posted Date: 1/22/2013 4:51:12 AM | Location : United States







Related Discussions:- Rolling - binder, Assignment Help, Ask Question on Rolling - binder, Get Answer, Expert's Help, Rolling - binder Discussions

Write discussion on Rolling - binder
Your posts are moderated
Related Questions
What is the easiest way to give proof the varignon''s theorem? Help please guys

At a large port facility near New York City tractor-trailer trucks are lined-up in long queues as their drivers wait to have their containers inspected and documents processed.  As


advantages and disadvantages in single flemish bond

I am a civil engineer and interested to teach.Is there any vacancy?

Describe about the Prestressed concrete Civil engineering structures, such as buildings, bridges, dams, towers etc. and their structural components such as beams, columns, slab

The plan of a proposed spoil heap is shown in Fig. The heap will stand on a thick deposit of soft clay with E-value 15 MN/m 2 . The uniform pressure on the soil may be suppose as 1


Define Limitations of Underwater Magnetic Particle Testing? As with any non-destructive test method, UWMT has some limitations as under: i. Underwater magnetic particle tes

A finish-to-finish activity is best described as: The "from" activity must finish before the "to" activity can finish The "from" activity must finish before the "to" acti