Rolling - binder, Civil Engineering

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.

Posted Date: 1/22/2013 4:51:12 AM | Location : United States







Related Discussions:- Rolling - binder, Assignment Help, Ask Question on Rolling - binder, Get Answer, Expert's Help, Rolling - binder Discussions

Write discussion on Rolling - binder
Your posts are moderated
Related Questions
solution of point of contraflexure

describe in detail the various parts of a total station


Q. Knife edge loads – representation of wheel axles? In BS5400 traffic loads for HA loading are given by uniformly distributed loads along loaded length and a knife edge load.

Define Drag load test of shock transmission unit? This test ensures that excessive load should not be transmitted to the structure by the STU. As per the test the STU shall hav

what is offset survey and how it is done

Calculate the ultimate compressive strength A 6 in. by 12 in. cylinder failed at an axial compressive force of 120,000-lbf, at 28 days. Calculate the ultimate compressive stren


We can measure concrete by Cubic feet, Cubic yards, Cubic Meter

plane table surveying is used commonly to survey small areas because