Rolling - binder, Civil Engineering

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.

Posted Date: 1/22/2013 4:51:12 AM | Location : United States







Related Discussions:- Rolling - binder, Assignment Help, Ask Question on Rolling - binder, Get Answer, Expert's Help, Rolling - binder Discussions

Write discussion on Rolling - binder
Your posts are moderated
Related Questions
Q. Evaluate the Length of guide bund? For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream

dek type bridge

Q. Describe the Consolidation Settlement? The resulting settlements which are time-dependent and are termed consolidation settlements. After the consolidation settlements take

Concordant Prestressing In this type of prestressing, tendons follow a concordant profile. The concordant profile of  tendons does not change the support reactions in a statica

Classification Based on Mode of Growth: On the basis of mode of growth trees are classified as (a) Exogeneous and (b) Endogeneous (a) Exogeneous Trees: These trees grow outwa

A -3.00% grade intersects a +1.25% grade at Sta. 85+80 and elevation 210.00 ft.  A 350-ft vertical curve connects the two grades.  Determine the station and elevation of turning po

A completely saturated sample of clay has a volume of 31.25 cm 3 and a weight of 0.5866 N. The same sample after drying has a volume of 23.92 cm 3 and a weight of 0.4281 N. Compu

Project specifications require a relative compaction of 95% (modified Proctor).  Construction of a highway embankment requires 10,000-yd 3 of fill.  The borrow soil has an in-situ

random rubble coursed, suare rubble coursed and uncoursed, polygonal walling, flint walling

contituents of paints