Rolling - binder, Civil Engineering

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.

Posted Date: 1/22/2013 4:51:12 AM | Location : United States







Related Discussions:- Rolling - binder, Assignment Help, Ask Question on Rolling - binder, Get Answer, Expert's Help, Rolling - binder Discussions

Write discussion on Rolling - binder
Your posts are moderated
Related Questions
how to draw load intensity and bending moment diagram form a given shear force diagram

how can we increase revenue to raise on fortune 500 list?

For the project network shown, the late start time (day) for activity "Q" is most nearly: Solution:  List the paths leading to "Q" and calculate the duration for each.

do u do drawing assignment ( 3rd angle projection)

What is the shrinkage factor

An intersection has a total entering traffic volume of 42,000 vehicles per day.  During the past three years, there have been a total of 35 reported intersection-related crashes.

Quality Control of Concrete Roads: Concrete roads require a very high degree of quality control. The following aspects need to be checked regularly: (a) Strength, shape an

dowel or aggregate interlock ?how to decide?

Reason of loading on alternative spans to obtain maximum positive moment in a span of a continuous beam To attain a maximum sagging moment in a span of a continuous beam, gene

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin