Rolling - binder, Civil Engineering

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.

Posted Date: 1/22/2013 4:51:12 AM | Location : United States







Related Discussions:- Rolling - binder, Assignment Help, Ask Question on Rolling - binder, Get Answer, Expert's Help, Rolling - binder Discussions

Write discussion on Rolling - binder
Your posts are moderated
Related Questions
description and details about distomat

An activated sludge tank treats 1 MGD from the primary clarify and has an X of 2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank and has


Compass Surveying: You have studied about the compass and its use for bearings of measuring survey lines. The angular measurements are carried out with prismatic compass that

Explain the Underwater Problems and Material Defects? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as

Why hybridisation never take in isolated atom

what is the bending stress for a simply supported beam with three equal concentrated loads that are equally spaced?

determine the maximum positive and negative shear shear

Q. Write short notes on Numerical rating of Bridges? In the numerical rating system, the condition of a bridge is represented by a number consisting eight digits. This eight di

write buckling and dislodging of brick slip?