Reason in checking the ratio (i.e. design flow to full-bore flow > 0.5) in circular pipe design
For checking of self-cleansing velocity for pipes, there is another criterion to check design flow Q to full bore flow Qfull> 0.5. If this criterion is met, it may be assumed that design flow is always greater than self-cleansing velocity.
The reason behind it is that from the chart of circular pipes when Q/ Qfull>0.5 then ratio of design velocity V to full bore velocity Vfull>1. After confirming Vfull>1m/s then it leads to V>1m/s. Therefore minimum velocity at full bore flow must be checked.
Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio
Q. Illustrate the Purpose of pedestals? When structural steel works are connected to foundation, pedestals are generally designed to carry loads from metal columns through grou
what are advantage of stepping stone
test in fresh concrete
Q. Evaluate the Length of guide bund? For encouraging axial flow through the bridge, upstream length of guide bund may be kept 1.0 to 1.5 times the bridge length and downstream
properties of coarse and fine aggregates
Ground Water Levels The location of the ground water level is essential for deep excavation, water-logged areas. The existing wells in the nearby vicinity of the proposed site
Resultant force at a section We can determine stresses at top and bottom fibres, at a section of a beam, due to pre-stressing force and external loads. Using them, we can draw
Explain some Important Points for Hazardous Waste The mixture rule prevents dilution of waste for the purposes of escaping RCRA regulation. Mixtures of a listed hazardous w
Geotechnical project specifications require that the soil's optimum moisture content of 24% be maintained during the roadbed's construction. The field moisture test finds that fi
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd