Program evaluation and review techniques, Mechanical Engineering

Program Evaluation and Review Techniques:

The Rola and Cola Corporation is a professional II nursing home aspiring to become I nursing home. It desires to provide the ultimate in nursing care for patients. The administrator prepares the list of activities, i.e.

i.     Perform pilot service for 6 patient in new facility,

ii.    put up the facility,

iii.   Install all equipment and furnishing,

iv.   Recruit staff of nursing home,

v.   Train the nurse staff, and

vi.  Pass security inspection of Municipal Building Authority.

The sequence of these activities is shown in Table

Table: Time Estimate of the Activities

 

1735_Program Evaluation and Review Techniques.png

The sequence relationship accomplishing the precedence constraints are illustrated in Figure. Then an arbitrary coding is adopted to make the node identification (Node-10 to Node-60). A dummy activity 40-50 is utilized in the diagram because activity A referred as activity 50-60, should be preceded by activity C, E and F. Now, the next step is to get the time estimate for each activity. Once the time estimate is obtained, then critical path, critical path times and slack times are calculated.

43_Program Evaluation and Review Techniques1.png

Figure: PERT Diagram

2254_Program Evaluation and Review Techniques2.png

Figure: PERT Diagram

First we calculate the expected time using the Eq. of μ For example, the expected time for activity is

μ = ( a + 4 m + b )/6

te = (20 + 4 (24) + 30)/6 = 24.3          

Likewise calculation is performed for all other activities and their results are illustrated in Figure. Now, the critical path is the path with the longest time through the network. But, there are three paths viz. 10 - 20 - 40 - 50 - 60, 10 - 20 - 50 - 60 and 10 - 30 - 50 - 60 with total expected time of 32.8, 45.1 and 12.6 respectively. Thus, the critical path is 10 - 20 - 50 - 60 with the critical path time of 45.1 weeks.

Posted Date: 1/31/2013 6:12:08 AM | Location : United States







Related Discussions:- Program evaluation and review techniques, Assignment Help, Ask Question on Program evaluation and review techniques, Get Answer, Expert's Help, Program evaluation and review techniques Discussions

Write discussion on Program evaluation and review techniques
Your posts are moderated
Related Questions
If crankshaft oil seal seating area found ok : Replace with a new oil seal and ensure the seal seats in the stator plate properly and while fixing the stator plate ensure using sta


The first stage of design assumes: budget is approved, marketing research is complete, product can be made at a price below that which it can be sold, research and development is c

how will u designate a v belt

A suspended walkway in an underground cavern consists of a deck supported by three tie rods placed symmetrically about the centre as shown below: The rods are each of

Prepare a design of close coiled helical compression spring for a service load ranging from 2250 N to 2750 N. The axial deflection of the spring for the load range is 6 mm. Conside

In designing rotating space stations to give for artificial-gravity environments, one of the constraints that must be considered is motion sickness. Studies have shown that the neg

ESSENTIAL S OF A GOOD BOILER: -     Should be capable of producing the required Steam at   the required pressure for minimum fuel required. -     Should be capable of stan

What is the difference between counter flow and parallel flow Heat exchange. Classify Heat exchange on the basis of constructional features and design.

Reduce system to a single force and couple: Q: A system of parallel forces is acting on rigid bar as shown in the figure given below. Reduce this system to  a single force