Predetermined time standard, Management Theories

The  procedure  for setting  a predetermined  time  standard is as follows:

1. Observe the job or think  it through  if it not yet  being  performed. It is best to  observe under typical  conditions: typical  machine  materials  and worker.

2. Itemize the job elements. Do  not be  concerned about  timing  them just  thoroughly document  all  the motions performed by the worker.

3. Form  a table  of predetermined time standards  record the standards  for each  motion units. Motion  units  are expressed in some  basic  (  a Therblig scale  is often used ) that  corresponds to time  units.

4. Find the  sum of the standards  for all  motions .

5. Estimate an  allowance for personal time, delays and fatigue and add to the sum  of standards .

This  total  sum is  the predetermined  time  standard for  the job.

Posted Date: 2/20/2013 12:26:20 AM | Location : United States







Related Discussions:- Predetermined time standard, Assignment Help, Ask Question on Predetermined time standard, Get Answer, Expert's Help, Predetermined time standard Discussions

Write discussion on Predetermined time standard
Your posts are moderated
Related Questions
Q. Define the term 'Planning Premises'? Planning principle is defined as the anticipated environment in which plans are expected to operate. Premises are the suppositions on wh

Experimentation: Experimentation is not easy to define. It will refer to that research process in which one or more variables are manipulated under conditions that permit the

Matrix Str ucture An organizational structure building two lines of authority (for example: combining functional and departmental lines of organization).

what effect has abc coss in selling price

#history of managment


Critically analyze Mr. vincent''s reasoning



Critically analyze Mr. vincent''s reasoning