Pre-stressing work, Civil Engineering

Assignment Help:

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?


Related Discussions:- Pre-stressing work

Calculate the total duration for the four activity project, Calculate the T...

Calculate the Total Duration for the Four Activity Project Solution:      Scheduling work activity has associated time duration. The durations shown in the Table were e

Cross sectional area to be excavate for roadway construction, The Table pro...

The Table provides the cross-sectional areas to be excavated for the roadway construction. The volume of earth to be excavated (yd 3 ) between section 83+65.6 and 85+98.5 is most n

Show the specification of bricks, Q. Show the Specification of Bricks? ...

Q. Show the Specification of Bricks? Specification of Ist class Bricks- 1. Table moulded and wire cut. 2. It should have edges and parallel faces. 3. If struck with ha

Calculate benefit cost ratio for government project, Calculate the Benefit-...

Calculate the Benefit-Cost Ratio for Municipal Government Project With interest at 10%, the benefit-cost ratio for this municipal government project is most nearly:   Initia

Tremie pipes are normally used with aid of hoppers, Question For underw...

Question For underwater concreting, tremie pipes are normally used with aid of hoppers. From time to time tubes are put in inside the hoppers and with reasons? Answer

Two way slab, how can i design reinforcement for a two way slab

how can i design reinforcement for a two way slab

Resultant pull, two locomotive moving on opposite bank of a canal can pull ...

two locomotive moving on opposite bank of a canal can pull a vessal parallel to the banks by the means of two rope.the force in the ropes are 20kN and 24kN while the total angle be

12/5/2013 6:27:14 AM

Throughout pre-stressing operation at one end, frictional losses resolve occur and pre-stressing force decreases along a length of tendon until reaching other end. These frictional losses include a friction induced due to change of curvature of tendon duct and also shake effect due to deviation of duct alignment from a centreline. Therefore, pre stress force in the mid-span or at another end would be greatly reduced in case frictional loss is high. Consequently, pre stressing, from both ends for single span for example pre stressing one-half of total tendons at one finish and remaining half at another end is carried out to allow an even distribution and to provide symmetry of pre-stress force along structure.


In actuality, stress at one end only has the potential benefit of lower price when compared with stressing from both ends. For multiple spans as in two spans with not the same span length, jacking is usually approved out at an end of a longer span so to provide a higher pre stress force at location of maximum positive moment. On opposing, jacking from an end of shorter span will be conducted if a negative moment at intermediate support controls pre stress force. However, if total span length is sufficiently long, jacking from the both ends has to be considered.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd