This assessment will test Learning Outcomes 3 and 4 as well as the component of Learning Outcome 1 as it refers to waste disposal for the Plumbing Technology. The student is expected to answer questions 1 and 2 to demonstrate his/her understanding of all the associated assessment criteria.

 You are a member of a design team in a consulting engineering company engaged by a developer. The developer requires preliminary designs for a complex in East Trinidad which aims at meeting the needs of the modern middle class family. The complex includes twelve (12) townhouses, a senior citizen retirement home and shopping centre with food court.

The townhouses are two (2) storey buildings, four (4) bedrooms, accommodate five (5) persons, master bathroom with bathtub, laundry and hot and cold water supply.

The senior citizen retirement home is central air condition two (2) storey building, provides accommodation for sixty (60) residents, fifteen (15) staff members, and a doctor's office with facilities to provide basic health care.

The shopping centre includes ten (10) stores and a food court with five (5) restaurant outlets.

Question 1

You are required to:

1. Produce a sketch plan showing the wastewater reticulation system for the complex.

2. Show how the foul water, rain water and surface water from the complex will be removed or reused on the complex.

3. Describe how the wastewater system for the complex will be tested and commissioned.

You are to ensure that all the requirements of the clients and buildings are met and that the designs comply with local regulatory standards for wastewater supply and solid and liquid waste disposal. You are to state all the assumptions made and provide a list of client and building requirements.

Question 2

You are required to:

a.  Describe what methods could be employed to dispose of the solid and liquid waste for the complex. 

b.  Utilise any latest technologies for recycling and recirculation of solid and liquid waste disposal on the complex.

c.  Provide simple sketch of pertinent/appropriate sections of the design depicting the system that will be utilized to achieve (a) and (b) above.

Posted Date: 2/21/2013 12:39:59 AM | Location : United States







Related Discussions:- Plumbing technology, Assignment Help, Ask Question on Plumbing technology, Get Answer, Expert's Help, Plumbing technology Discussions

Write discussion on Plumbing technology
Your posts are moderated
Related Questions
Determine the Characteristic Load for structure The Load, which has 95 percent probability of not being exceeded during the life of a structure, is considered as characteristic

A 4-m-long, 6-cm-diameter cylinder placed normal to the flow is used to measure the velocity of an air stream. If a force of 50 N is measured, the air velocity is nearest (for air

Indian Standard Codes All of the major countries like India, UK, USA, and Australia have their own standards for material standards, design procedures, testing standards, and



grading classification

Physical Tests on Cement (a) Soundness Test: by sieve analysis, it is conducted. 100 gms of cement is taken and sieved throughout IS sieve No. 9 for fifteen minutes. Residue on

Explain Chlorine Residuals Free Chlorine Residuals: Cl 2 , HOCl, OCl-   Combined Chlorine Residuals: Chloramines (mono, di and tri chloramines) The disinfecting ability o

chaining on level surface

Design a 10 unit rapid sand filter system for a flow of 6.3 MGD with a filtration rate of 2 gpm/sq ft. and an L: W ratio of 1.3.   Design flow (Q) = 6.3 MGD = 6.3x106 gpd =