Output of quality planning process, Other Management

Output of quality planning process

Quality management plan is one of the major outputs of quality planning. It describes how the project management team will implement  the quality process.  According  to  ISO  9000,  it  should  describe  the  project  quality system which includes the       organisational structure, responsibilities, procedures, processes, and resources required to implement quality management.

A quality management plan defines the quality threshold.    Quality management   plan   applies   to   project   deliverables   and   project   work processes. It provides input to the overall project plan and must address quality control, quality assurance, and quality improvement for the project.

Although the  entire quality requirements are not  clear  when  the quality management plan is being developed, we need to describe the processes and techniques that will be used to uncover the quality requirements and help in ensuring that all the quality requirements are met. The following are the information included in the quality plan:

  • Roles and responsibility: This lists the various quality related roles on the project and the set of quality activities for which the players would be responsible. The various quality related roles are quality auditors, third- party testing specialists, and inspectors and so on.
  • Completeness and correctness criteria: The team has to directly work with the clients and understand the client's perspective of completeness and correctness and document them as part of the quality management plan.
  • Quality requirement process: This describes the processes that will be used to ensure customer's quality expectations are properly captured and met.
  • Quality assurance activities: This describes the major quality assurance activities and techniques that will be implemented on the project.
  • Quality control activities: This describes the major quality control activities and techniques that will be used on the project.
  • Quality standards: This lists all quality standards that the company has previously followed and is applicable to the current project.
  • Quality tools: Lists any quality related tools the project will utilize.

The other outputs of quality planning process are:

  • Quality metrics: This is an operational definition that describes, in very specific terms, a project or product attribute and how the quality control process will measure it.
  • Quality checklist: A checklist is a structured tool, used to verify if a set of required steps have been performed. These are also used in quality control process.
  • Process improvement plan: This details the steps for analysing processes to identify activities which enhance their value. The areas to be considered are:
  • Process boundaries: Describes the purpose of processes, their beginning and end, their inputs/outputs, the data required, the owner, and the stakeholders.
  • Process configuration: This is a graphic depiction of processes, with interfaces identified and used to facilitate analysis.
  • Process metrics: Along with control limits, these metrics allow analysis of process efficiency.
  • Targets for improved performance: These guide the process improvement activities.
  • Project document updates: Project documents that may be updated include stakeholder registry and responsibility assignment matrix which describes the participation by various roles in completing tasks or deliverables for a project or business process.
Posted Date: 9/28/2012 5:19:06 AM | Location : United States







Related Discussions:- Output of quality planning process, Assignment Help, Ask Question on Output of quality planning process, Get Answer, Expert's Help, Output of quality planning process Discussions

Write discussion on Output of quality planning process
Your posts are moderated
Related Questions
QUESTION 1 SWOT Matrix is one of the principal tools for strategic analysis. Referring to this matrix- (a) Explain what you understand by internal analysis (b) Explain wh

Disadvantages of contracting  As we saw some of the factors that drive a contracting decision, now let us understand the disadvantages or criticisms associated with contracting

QUESTION 1 (a) Identify and critically discuss the different phases involved in the road map to ISO 9001:2008 Certification (b) ISO 9001:2008 is based on a framework known a

AA Code of 1908: Cataloging rules: author and title entries / compiled by Committees of the Library Association and the American Library Association. - English edition. - Lond

Library service is, in essence, the retrieval and dissemination of embodied knowledge to individual members and groups in a community. Hence, the two essential parameters which aff

Car Management System: You have been approached by a Used Car Dealership who wishes to introduce an IT system to support their business. You are required to implement a protot

QUESTION 1 (a) Every organisation must focus on quality performance. With the help of a schematic diagram, define the following terms as applied to management performance and i

Pigeon hole type in Periodical Display Rack-library furnitur in library management it has two parts, one is a cupboard in the bootom and the other pigeon holes at the to,-Over

Question 1 Define conflict. Discuss four ingredients of conflict Question 2 Discuss four different types of conflicts which may occur in any organization Question 3 List

Types: There are various types of survey research-descriptive,  evaluative, comparation, correlation, longitudinal, cross-sectional, cross-cllltural, etc.  Descriptive  Survey: