Methods of constructing roads in marshy areas, Civil Engineering

Methods of Constructing Roads in Marshy Areas:

The following methods are adopted for constructing roads in marshy areas:

(a) Removal of soft soil and replacement with good soil.

(b) Displacement of the soft soil by constructing the embankment and blasting the soft soil, such that the embankment displaces and occupies the space occupied by the soft soil.

(c) By constructing the embankment in stages, allowing settlement to take place, and if necessary to construct the embankment to a level above the designed level, and removing the excess material after full settlement has taken place.

(d) By providing vertical sand drains (0.4-0.6 m dia) which will facilitate the upward movement of water from the underlying saturated soil and drain it away. Figure gives a typical layout of sand drains.

1906_Methods of Constructing Roads in Marshy Areas.png

Figure: Vertical Sand Drains

Posted Date: 1/22/2013 6:13:23 AM | Location : United States







Related Discussions:- Methods of constructing roads in marshy areas, Assignment Help, Ask Question on Methods of constructing roads in marshy areas, Get Answer, Expert's Help, Methods of constructing roads in marshy areas Discussions

Write discussion on Methods of constructing roads in marshy areas
Your posts are moderated
Related Questions
Bituminous Macadam: Bituminous Macadam (BM) is a base course in which coarse aggregates are mixed with a bituminous binder. The mix is open-graded with 20-25 per cent voids.

Normal approximation to compute the probability: A lot contains 100 articles of which 10 are defective. The lot is rejected if a random sample of 10 articles drawn from the lo

slope deflection with settlement


Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.


A pre- engineering base line was run down a very steep hill.rather than measure horizontaily down hill with steel tape: surveyor measured the vertical angle with the theodolite and


In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

reparation of subgrade in sqm for a road of span 12 km and width 5.25m,with shoulders of 0.75m span on both the sides...considering extrawidening too......plz help...i m preparing