Meter Field Testing - Sealing Points

The meter seal should be tamper proof. The consumer should be briefed about seals. The sealing of all metering systems should be completed at several points (as applicable) to prevent tampering. There should be at least one seal at all points described below (wherever applicable):

a) CT Secondary Boxes (further to locking arrangement)

b) PT Secondary Box (further to the locking arrangement)

c) Meter Cabinet

d) Meter Test Block

e) Meter Terminal Cover

f) Meter Cover

g) Panel doors where CT and PT secondary circuits are terminated or whereas possibility for shorting or breaking exists and fuses/links are given.

h) PT selector relay box where automatic change-over of potential supply to meter from one PT to another is given

i) CT Primary Links and Top Covers

j) MD Reset Push Button

k) Boxes/Cabinets containing terminals for remote transmission of metered data through communication channels, junction boxes in the system and boxes wherein interface devices are mounted.

l) Meter reading port.

Seals are essential to guard against the tampering of connections and internal elements of a meter. Tampering of seals will provide consumers access to the relevant part of a meter installation where s/he could manipulate the unit to record less energy leading to commercial loss. A seal is placed to detect unauthorized entry to the meter internals. The effectiveness of the seal depends on the category of seal (whether it is tamper proof or not, whether a duplicate could be acquired or not, etc.), and the procedures used in tracking the seals.

Posted Date: 2/6/2013 8:16:57 AM | Location : United States







Related Discussions:- Meter field testing - sealing points, Assignment Help, Ask Question on Meter field testing - sealing points, Get Answer, Expert's Help, Meter field testing - sealing points Discussions

Write discussion on Meter field testing - sealing points
Your posts are moderated
Related Questions
Q. Working of self - excited generators? For self-excited generators, residual magnetism must be present in the ferromagnetic circuit of the machine in order to start the self-

a) With the help of a neat and clean sketch illustrate the difference between relative and absolute motion measuring device. b) Discuss electromechanical methods for calculating

a 49pf cap,a 50 uH inductor, and a 100 ohms resister are in parallel: what is the resonance freq? And what is the complex impedance vector at 100MHZ?

how does this circuit work and what are th electrical components in it do?

Q. For an n-channel JFET with V A = 350 V, I DSS = 10 mA, and V P = 3V, find V DS that will cause i D = 11 mA when v GS = 0.

Logical Operations Various  operations like and  or exclusive  or complement compare and rotate are called  logical  operations. Generally flags ( not all always) are modified

Q. A transistor in a fixed bias amplifier circuit was replaced by another transistor of beta equaling 150 instead of 60.if IB of transistor is equal to 100 microampere and collecto

Q. Two single-phase transformers, each rated 2400: 120-V, are to be interconnected for (a) 4800:240- V operation, and (b) 2400:120-V operation. Draw circuit diagrams and show polar

What is limitor.. how it works

Q. To answer the following question, please refer to the figure below. Concentrating only at the upper right quadrant, discuss the foreign exchange market equilibrium. Answer: