Measuring kanban, Business Management

Measuring Kanban

 Two commonly cited methods of measuring the performance of a manufacturing process are flow through time and work in progress inventory levels.

Flow through time is takes once unit to pass through the entire process from start to finish ( on average) . in the kanban system both of these measures are at least partially dependent upon lot sizes.

For example if a kanban system uses 25 workstations and a lot size of 54th the average WIP will be near 100 units. If the cycle time for a balanced load is say two minutes per item ( using the lot size of 4 ) . flow through time will be close to 200 minutes (allowing for some variation) : one unit of product will flow through the system in 200 minutes.

Posted Date: 3/1/2013 4:09:50 AM | Location : United States







Related Discussions:- Measuring kanban, Assignment Help, Ask Question on Measuring kanban, Get Answer, Expert's Help, Measuring kanban Discussions

Write discussion on Measuring kanban
Your posts are moderated
Related Questions
QUESTION 1 a) What is communication? b) Discuss four common types of communication barriers c) Explain five strategies for overcoming communication barriers and briefly e

The organization that administers the certification programs for Certified Hotel Account Executives and Certified Hotel Technology Professionals is: Answer

Q. Explain the advantages and disadvantages of partnership? Advantages of Partnership Firm 1. Easy formation: A partnership firm can be formed without any compulsory lega

Explain about the participation in management of workers. Workers’ Participation in Management: Worker’s participation into management can be in any of shape, through est

Select a small business of your choice and explain how the particular business can be considered as a small business enterprise. List the advantages and disadvantages of being a sm

Explain about the programmed and non-programmed managerial decisions. Programmed and Non-Programmed decisions: Programmed decisions are which made in accordance along wit

55 is a participative programme. It is a effective approach of improving the work environment and total quality. It become a base for continuous improvement in the organizatio

Problem Write short notes on partnering? a) Three broad categories of relationships(Adversarial, Barometric, Complementary) b) Goals of partnership(Reduction in waste , S

Question 1: (a) Explain the Communication Process Model and elaborate sequentially through the use of this model the various stages that can ensure effective business communic

What factors affecting Morale? Factors Affecting Morale is as illustrated below: Factors that tend to lower or enhance the employee morale are as follows: a. Job Factors: