Master production schedule, Mechanical Engineering

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.

Posted Date: 2/1/2013 1:07:02 AM | Location : United States







Related Discussions:- Master production schedule, Assignment Help, Ask Question on Master production schedule, Get Answer, Expert's Help, Master production schedule Discussions

Write discussion on Master production schedule
Your posts are moderated
Related Questions
A pelton wheel works at the foot of a dam because of which the head available at the nozzle is 400m. The nozzle diameter is 160mm and the coefficient of velocity is 0.98. The diame

full defination

The Ordinate Dimension Command We can use The Ordinate command to annotate co-ordinate points with X or Y values. This might be useful for setting-out on site plans.

EXPLOSIVE WELDING I CLADDING In this process, two pieces of metal are impacted together at an extremely high velocity of impact achieved by the detonation of an explosive cha

Describe method of deliberately placing column from centre in footing. The method of deliberately placing a column away from the centre of the footing so that resulting soil pr

Drive a mathematical expression for moment of Inertia of a rectangular section. A body consists of a solid hemisphere of radius 4 cm and a right circular cone of height 12 cm. t

Evaluate the motion of system: Q : Block A and B are connected by a rigid horizontally bar planed at each end are placed on the inclined planes as shown in the figure giv

a) Determine a root of the equation x-cosx =0 using Bisection method correct to three decimal places. b) Determine smallest possible root of the equations x-e -x =0 using Regul

analyze a six bar linkage to get the position, velocity and acceleration

Q. Cyclic Service for vessels? The required service for all vessels shall include consideration of cyclic service. Batch operation vessels, for example, quite frequently fall i