Master production schedule, Mechanical Engineering

Assignment Help:

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.


Related Discussions:- Master production schedule

Equilibrium, cases of equilibrium with explaination

cases of equilibrium with explaination

Explain about the pedestals as construction engineering, Explain about the ...

Explain about the pedestals as construction engineering. Introduction of pedestals enables the construction engineers to make up levels to supply larger bearing areas to the fo

Standard for steel pipes, Q. Standard for steel pipes? Vendor shall mee...

Q. Standard for steel pipes? Vendor shall meet or exceed the requirements of the latest edition of the following codes, regulations, and standards except as superseded herein.

What are the approaches to the design of retaining walls, What are the appr...

What are the approaches to the design of retaining walls? The approach to the design of retaining walls can be started as follows: a. Chosse a trial dimension of the wall

Physics, when object is placed beyond the center of concave mirror

when object is placed beyond the center of concave mirror

Alignment of a railway line - railways, Alignment of a Railway Line: ...

Alignment of a Railway Line: Selection of Alignment The following points must be considered in selecting the alignment of a railway line : (a) It should be as direct

MATERIAL SCIENCE, IF ONE SOLID PHASE SPLITS INTO TWO SOLID PHASES ON HEATIN...

IF ONE SOLID PHASE SPLITS INTO TWO SOLID PHASES ON HEATING THE REACTION IS CALLED

Carnot vapour cycle - thermodynamics processes, Carnot vapour Cycle: I...

Carnot vapour Cycle: It is convenient to analyze the performance of steam power plants by means of idealized cycles that are theoretical approximations of real cycles. The Car

Evaluate the angle of heel, A motor cycle with its rider, weight 250kg, the...

A motor cycle with its rider, weight 250kg, the centre of gravity of the machine and rider combined being 60cm above the ground level when the machine is standing upright. Each roa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd