Master production schedule, Mechanical Engineering

Master Production Schedule:

A manufacturing unit produces two products M and N on generates to stock basis. The estimated demand for the product M and N over the next six week are illustrated in the following Tables (a) and (b).

Table (a) : Demands for Product M from All Sources

 

2027_Master Production Schedule1.png

The amount for the safety stock for product M is 50 and for product N is 40. The fixed lot size for M is equal to 70 and for N are 80. The starting inventory for M is 90 and for N are 70. Make a Master Production Schedule (MPS) for the product M and N.

Solution

For both of products M and N, take the total demands, consider straining inventory, determine in which weeks ending inventory would fall below the safety stock and therefore require production and schedule a lot of the product to be generates during those weeks.

Table (c): Master Production Schedule (Number of Product M and N)

 

1787_Master Production Schedule2.png

In week 1, the balance exceeds the wanted safety stock; thus no production of product M is needed.

In week 2, the balance is also adequate to provide the desired safety stock and no production of product M is needed.

In week 3, the balance would be negative in fact if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in third week.

In week 4, the balance would actually be negative if production of M where not scheduled thus a fixed lot size of 70 product M is scheduled in fourth week.

In week 5, actually the balance would be negative if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in fifth week.

In week 6, the balance would be negative actually if production of M where not scheduled hence a fixed lot size of 70 product M is scheduled in sixth week.     

Table (e) : MPS for Product N

2478_Master Production Schedule3.png

In week 1, the balance exceeds the wanted safety stock; therefore no production of product N is needed.

In week 2, the balance would actually be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in second week.

In week 3, the balance is also sufficient to provide the desired safety stock and no production of product N is needed.

In week 4, actually the balance would be negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fourth week.

In week 5, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in fifth week.

In week 6, the balance would actual negative if production of N where not scheduled hence a fixed lot size of 80 product N is scheduled in sixth week.

Posted Date: 2/1/2013 1:07:02 AM | Location : United States







Related Discussions:- Master production schedule, Assignment Help, Ask Question on Master production schedule, Get Answer, Expert's Help, Master production schedule Discussions

Write discussion on Master production schedule
Your posts are moderated
Related Questions
COMPARISON WITH CAM MECHANISMS WITH LINKAGES

Conveyor and auger Two Hydraulic motors are provided for individual control of two conveyors and Auger, which are provided for individual control of material on both the sides

question no 2,page no 84 of strenght of materials by G H Ryder

Crank Pin and Crank Shaft - Part of combustion engine: Cran k Pin: Crank pin is region on crank shaft on which big end of connecting rod is attached. These pins are eccentr

Illustrate the Types of special foundations Special foundations find use under following situation: i)  To meet the demands that are arising from uncommon environmental cond

Do the answers come with the full calculations?

history of electronics materials

A column is made from a universal I-section 203x 203 x 60. A load of 96kN is applied on the y-axis offset 50mm from the centroid. Calculate the stress at the outer edges of the y-a


Holonic Manufacturing System Holonic manufacturing implies a highly distributive organization of the manufacturing systems. Intelligence is distributed between the individual e