Linear Programming, Operation Research

A paper mill produces two grades of paper viz., X and Y. Because of raw
material restrictions, it cannot produce more than 400 tons of grade X paper
and 300 tons of grade Y paper in a week. There are 160 production hours in a
week. It requires 0.20 and 0.40 hours to produce a ton of grade X and Y papers.
The mill earns a profit of Rs. 200 and Rs. 500 per ton of grade X and Y paper
respectively. Formulate this as a Linear Programming Problem.
Posted Date: 2/10/2013 9:04:56 AM | Location : USA







Related Discussions:- Linear Programming, Assignment Help, Ask Question on Linear Programming, Get Answer, Expert's Help, Linear Programming Discussions

Write discussion on Linear Programming
Your posts are moderated
Related Questions
These models are applied to the management ( planning controlling and scheduling ) of large scale projects. PERT/ CPM techniques help in identifying potential trouble spots in

Discuss the methodology of operation research

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Rank Methods Spearman s When the variables  under  consideration are  not capable  of quantitative  measurement but can  be arranged  in serial  order( ranks) we find  correla

Uses of Mode The  use of the mode is recommended in the following  situations: a.When a quick  and approximate measures of  central tendency desired. b.When the  measure

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2, Subject to the constraints: X1+ X2 = 4 X1+ X2 = 2 X1, X2 = 0

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Uses   of Standard Deviation Normal 0 false false false EN-IN X-NONE X-NONE


Machine  Tabulation This methods  of tabulating information  is generally used in  case of extensive  large scale  surveys. Mechanical sorting and tabulating equipments and su