Length is constructed in first phase of construction, Civil Engineering

Assignment Help:

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construction?


Related Discussions:- Length is constructed in first phase of construction

Rcc, what is the density of rcc

what is the density of rcc

Define underwater inspection of steel or cast iron structure, Define Underw...

Define Underwater Inspection of steel or cast iron structures? Underwater Inspection of steel/cast iron structures may be carried out as under: i. Start the inspection at sp

Open channel, design of irrigation channel permissible velocity table

design of irrigation channel permissible velocity table

Geometric design, calculating OVERTAKING SIGHT DISTANCE

calculating OVERTAKING SIGHT DISTANCE

Write short note on pressure filter, Q. Write short notes on Pressure filte...

Q. Write short notes on Pressure filter for drinking water supply. What are pressure filters and what are its advantages / disadvantages over the normal filter bed. What is p

Roofs, describe the general principle of roof design

describe the general principle of roof design

How to calculate the total loss of prestress, How to calculate the total lo...

How to calculate the total loss of prestress As a general guide, it may be taken that total loss of prestress may be in the range of 20 to 25 percent of the initial prestress,

Yield, Describe the process of yielding and state the effect work hardening...

Describe the process of yielding and state the effect work hardening has on the yield point of mild steel

Purpose of the gap in the road on this bridge, What is the purpose of the g...

What is the purpose of the gap in the road on this bridge? Ans) Purpose of the gap in the road is to permit the road to expand and contract with temperature alters without causi

12/5/2013 6:44:00 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

12/5/2013 6:45:29 AM

Mostly, there are primarily three reasons for this arrangement-
(i) Permanent structure is statically indeterminate structure. all through construction by using span-by-span construction, if first stage of construction contains of first span length L only, then a sagging moment in mid span of partially completed bridge is big than that of completed two-span permanent structure.
To pass up such occurrence, 0.25L of bridge segment is extended further from second pier which offers a counteracting moment, thereby reducing mid-span moment of partially completed bridge.
(ii) The place of 1.25 L countering from first pier is approximate location of point of contra flexure, imagine that two-span Bridge is uniformly loaded in which bridge moment about zero in an event of future is loaded bridge.
Therefore, designing of construction joint in this particular location has least adverse effect on structural performance of a bridge.
(iii) In case of a pre stressed bridge, pre stressing work has to be carried out after construction of first segment of bridge. If pre stressing work is performed at first pier which is heavily reinforced with reinforcement, it is adverse when compared with pre stressing location at 1.25L from first pier everywhere there is relatively new space to accommodate pre stressing works.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd