Implementation of material requirement planning, Mechanical Engineering

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.

Posted Date: 2/1/2013 12:52:38 AM | Location : United States







Related Discussions:- Implementation of material requirement planning, Assignment Help, Ask Question on Implementation of material requirement planning, Get Answer, Expert's Help, Implementation of material requirement planning Discussions

Write discussion on Implementation of material requirement planning
Your posts are moderated
Related Questions
I have literature review and the title is "the effect of fluid cooling on the performance of building integrated photovoltaic thermal systems. Using some BIPVT prototypes measure

I am studying in Final Year of Engineering(Mechanical) and I would like some help for the project. It will be helpful if you suggest some project related to Automation.

Spindle complaint Gear shift : Check spindle comp. Gear shift for bend, rust, arms for bend and arm spring condition and availability.

what is a deficient frame?

Condition for Carnot theorem - thermodynamics: 1 .   If T 1  = T 2 ; No work, = 0 2 .   Higher the temperature difference, greater the efficiency. 3.   For the same

The first laboratory report, covering the two-part exercise involving tension testing and stress concentrations is due in lab two weeks after the conclusion of fatigue testing.

Q. What do you mean by turret Nozzle? Turret Nozzle - Turret nozzles are large nozzles that can deliver large quantities of water quickly. They are used on very large fires whe

T ensile Stress: The stress induced in a body, when subjected to two equal and opposite pulls as shown in figure (a) as a result of which there is an increase in length,

A triangle ABC with vertices A (30,20), B(90,20), C(30,80) is to be scaled by a factor of 0.5 about a point X(50,40). Calculate :- (i) The composite transformation matrix; and

what is function of orifice