Implementation of material requirement planning, Mechanical Engineering

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.

Posted Date: 2/1/2013 12:52:38 AM | Location : United States







Related Discussions:- Implementation of material requirement planning, Assignment Help, Ask Question on Implementation of material requirement planning, Get Answer, Expert's Help, Implementation of material requirement planning Discussions

Write discussion on Implementation of material requirement planning
Your posts are moderated
Related Questions
Find out also the loss of energy through impact: Example 1. A bullet weighing 0.1 newton horizontally fired with a velocity of 80 metres/sec hits a wooden block, weighin

Describe vibration, How to calculate vibration?

how to calculate the distribution of shear force and bending moment for a simply supported beam

Q. Explain about Master Stick File? The Master Stick File is an up-to-date version of the P&IDs; it is not to be used as a check print by any discipline. Miscellaneous comment

First we focus on the inner region fluid (0 (solid body rotation) around the z-axis. The steady incompressible velocity field is given by ur=0 utheta=rw uz= 0. The pressure at th

Q. Explain working of Tubesheets? The tube and tube pitch selected shall be approved by WorleyParsons Canada. The preferred tube pitch shall be a minimum of 1.3 x tube OD and

Vented Causeway: Vented causeways are structures provided with vents (usually pipes) to take care of dry weather perennial flows and which allow water to overflow the paved b

EFFECT OF PROCESS PARAMETERS High voltage gives high velocities in the electron beams. The mutual repulsion effects in the constituent electrons will be less marked at high vel

The mass flow rate is 28kg/s in an axial flow gas turbine that develops 3.5MW. The stagnation conditions are 780KPa and 730 deg.C. at the entry. At the exit of the nozzle, the stat

Types of Splitwedge gate arrangement need to understand