Implementation of material requirement planning, Mechanical Engineering

Implementation of Material Requirement Planning:

The total requirements for a material from an MRP schedule are given in the following table :

                                                                                       Week

 

2442_Implementation of MRP.png

 The annual demand for this end item is estimated to be 25,000 units over a 50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to change over the machines in the ultimate assembly department to this end item when a production lot is begun. It costs Rs. 1.10 per unit when one unit of this product must be carried in inventory from one week to another; thus, when one unit of this product is in ending inventory, it should be carried over as beginning inventory in the next week and incurs the Rs. 1.10 per unit carrying cost. Find out which of these lots sizing methods results in the least carrying and changeover (or order) costs for the eight week schedule:

1.      Lot for Lot (LFL),

2.      Economic Order Quantity (EOQ), or

3.      Period Order Quantity (POQ).

Solution

 (a)       Develop the total carrying costs over the eight week schedule for the lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net requirement in each period.

 

1051_Implementation of MRP1.png

Ordering costs = Numbers of orders × 800.00 = 8 × 800.00 = 6400.00

 (b)       Develop the overall carrying costs over the eight week schedule for the EOQ lot sizing method. EOQ production lots equal the computed EOQ. First, compute the EOQ :

447_Implementation of MRP2.png

Carrying costs = total of ending inventories × 1.10 = 3266 × 1.10 = 3592.60

Ordering costs = Number of orders × 800.00 = 5 × 800.00 = 4000.00

 (c)       Develop the overall carrying costs over the eight week schedule for the POQ lot sizing method. POQ production lots equal the net requirements for POQ computed periods.

First, compute the POQ:

POQ = Number of weeks per year/ Number of order per year

=          50/(D/ EOQ) = 50/(25000/853)

= 1.706 or 2 weeks per order

 

2068_Implementation of MRP3.png

Carrying costs= sum of ending inventories × 1.10 = 2500 × 1.10 = 2750.00

Ordering costs = Number of orders × 800.00 = 4 × 800.00 = 3200.00

Among the lot sizing methods considered for this data, the POQ method exhibits the least carrying and ordering cost for the eight week net requirements schedule.

1. Where is MRP implemented?

2. Explain different lot sizing methods.

Posted Date: 2/1/2013 12:52:38 AM | Location : United States







Related Discussions:- Implementation of material requirement planning, Assignment Help, Ask Question on Implementation of material requirement planning, Get Answer, Expert's Help, Implementation of material requirement planning Discussions

Write discussion on Implementation of material requirement planning
Your posts are moderated
Related Questions
A jet of water moving at 8 m/sec. impinges on a concave-shaped vane to deflect the jet through 120 o when stationary. If the vane is moving at 5 m/sec., determine the angle of jet



ELECTRIC RESISTANCE WELDING Electric resistance welding is an important and widely applied non fusion welding process. This write up covers the basic principles of various resi

Step s for Method of Joint: To find force in member of the truss by this method, the three Steps which are given below are followed. Step-1 : Calculate reaction at su

Q. Explain Sand and moulding sands? Sand according to the amount of clayey matter they contain, the moulding sands are classified as: • Silica sand: Up to 20% clay. •

Qusetion: A body when projected vertically up covers a total distance s, during its time of flight. If we neglect gravity then how much distance, the particle will travel during

You need to sketch shear force and bending moment diagrams and estimate maximum bending and shear stresses acting on the beam using your knowledge in beam analysis.  Please note

Breather tube : Check breather tube for blockage and also air filter box hole where breather tube is connected, for any blockage.

Q. What do you mean by Moulding materials? Various types of materials are used in the foundries for the manufacture of casting moulds and cores. These materials are divided in