Illustrate network diagrams and bar charts, Project Management

Network diagrams and bar charts have different parts to play within planning a project. Where each of such tools used is and what does this demonstrate?

The network diagram displays and analyses the dependencies among the tasks or deliverables onto a project and this is used to classify the streams of work which can be undertaken in parallel. The bar chart demonstrates all of the tasks placed against a timeline to demonstrate while they are to be completed. The network diagram does not demonstrate this contrast along with the timeline very well, while on the bar chart the dependencies among tasks is not essentially self-apparent. The network diagram has other utilisations, for example into analysing the potential result of slippages and risks onto the attainment of the project's deadlines.

Posted Date: 9/2/2013 7:45:46 AM | Location : United States







Related Discussions:- Illustrate network diagrams and bar charts, Assignment Help, Ask Question on Illustrate network diagrams and bar charts, Get Answer, Expert's Help, Illustrate network diagrams and bar charts Discussions

Write discussion on Illustrate network diagrams and bar charts
Your posts are moderated
Related Questions
Identifying Project Risk  Risk identification is a process which determines the types of risks that have potential impact on a project. The risk identification is an ongoing pr

What is Buffering in risk management? Buffering: Buffering or slack is the allowance of additional cost, resources or time for example ‘just in case’ specific events or r

why is project cost considered the most important factor in project management?


using the operating cycle and any other financial management knowledge,discuss the applicabilty of such cycle to poultry

What is Trial Balance? Trial Balance: After posting each and every journal entries within the ledger, a statement termed as trial balance is prepared to check the accurac

GBF Group is a leading food and beverage manufacturer with an international presence in over 50 countries worldwide. The group has seven strategic business units (SBUs) and each ha

Question: (a) What could be the motivations for a large multinational to offshore its application development? (b) What could be the risks of offshoring application develo

However proving a design defect can be difficult. Some of the factors used by the jury to asses s whether a product design is defective and unreasonably dangerous are: 1.The utili

T, a member of the finance team, has been constantly arriving late to work and in recent months he has consistently made significant errors in his work. A number of colleagues have