Identify the characteristics of the organisation, Project Management

Assignment Help:

M is a business that sells custom made computer-based information systems. Every customer order is for a unique system, which will contain experts from many functional areas within M. Every customer expects a high level of individual attention. Some systems take only four to six months to design and form and cost less than €50,000, whereas other systems cost various million Euros and can take up to three years to complete. Projects are continually being done and started. 

Identify the characteristics of the organisation that make it suitable for M to have a matrix structure.

The characteristics of M that are appropriate to it adopting a matrix organisational structure are as follows:

  • The business of M having of a series of projects which are custom made, which are difficult and require staff from a number of dissimilar functional areas;
  • The projects undertaken by M have dissimilar start and end dates, so the organisation is continually reassigning resources from project to project as single ends and another begins;
  • The projects undertaken by M are difficult so the staff benefit from also being assigned to a technical function (like as finance or procurement) where they can share knowledge and experience with colleagues in their functional teams;

 


Related Discussions:- Identify the characteristics of the organisation

Aim and objective of syringe management plan, Aim The purpose of the Sy...

Aim The purpose of the Syringe management plan is to protect the social community against injury by syringe and help people manage syringe in proper manner. According to the re

Case study, two boss problem case study

two boss problem case study

Functional requirements for an exhibition management system, Question: ...

Question: (a) Consider the following quality goals and provide a way to make the goal more tangible such that it can be easily verified: i. Software should be user friendl

Layout planning and analysis, Layout Planning and Analysis Designing a...

Layout Planning and Analysis Designing and installing a layout for the first time and subsequent revision may be looked after by the. Engineering or planning department. Not i

Parameters of facilities planning and design, Question 1: Distinguish b...

Question 1: Distinguish between innovation and renovation within the parameters of facilities planning and design. Question 2: Although security and safety at the work

Explain portfolio management in project, Question: (a) Project plans ar...

Question: (a) Project plans are created in knowledge areas throughout the different phases of the project life cycle and are subsidiary components of the overall project manag

High performing multi-disciplinary management team, GBF Group is a leading ...

GBF Group is a leading food and beverage manufacturer with an international presence in over 50 countries worldwide. The group has seven strategic business units (SBUs) and each ha

The purpose of a project initiation document, S Company has been awarded th...

S Company has been awarded the contract for the refurbishment of a local hotel. The overall timescale for the project has been agreed at 30 weeks (a high fast completion for this s

Potential side effects of the tqm initiative, Question: "Total Quality ...

Question: "Total Quality Management is regarded as a quick fix solution by many organizations.This has led various companies to start on the road to total quality improvement i

Phases of value engineering process, P hases of value engineering process ...

P hases of value engineering process I nvestigation phase: This phase investigates the background information, the technical input reports, the field data, the functiona

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd