Gantt chart, Operation Management

Gantt Chart

The Gantt chart were made by Henry L. Gantt approximately a century ago. Their aim is to provide an immediate comparison between schedule and realty( i.e. among planned work and actual progress of the work). This is attained simply by marking on the chart the planned work and the actual progress of the work.The Gantt chart is in fact a modified bar chart in which horizontal bars are drawn for every activity in proportion to the time required for completing it. A cursor attached to the Gantt chart can be moves across the chart to compare among the actual progress and planned work till any particular date.

There are fundamentally two types of Gantt charts:

1. Order /Activity progress chart
2. Machine Load chart

In Gantt chart time in weeks or days is marked together the horizontal axis and the activities or orders are presented along the vertical axis. The amount of work planned or scheduled is marked by the firm lines or blank areas and the actual progress of the work by dotted lines or shaded areas.

Posted Date: 2/1/2013 8:13:45 AM | Location : United States







Related Discussions:- Gantt chart, Assignment Help, Ask Question on Gantt chart, Get Answer, Expert's Help, Gantt chart Discussions

Write discussion on Gantt chart
Your posts are moderated
Related Questions
Complete a net material requirements schedule for: a) All items (10 schedules in all), assuming the requirement for each BOM item is 1. b) All 10 items, assum

Compare and contrast Deming and Crosbys views on the cost associated with a lost customer.

Mr. McNeely currently batches orders for processing under the manual order management system. The orders are batched for daily processing. If Mr. McNeely opts to implement a Web-ba

Point  Rating Method In  selecting  a site  of location companies  have several  objectives, but  not  all are  of equal  importance. The relative weight a company assigns to

The Electro comp Corporation manufactures two electrical products: air conditioners and large fans. The assembly process fo each is similar in that both require a certain amount of

Using the data, suppose the manufacturer has an inflated demand forecast as follows: Quantity Probability 2,200 5% 2,300 6% 2,400 10% 2,500 17% 2,600 30% 2,700

Consider how these 10 Golden Rules apply to all projects and apply three of them to your project.

How is anticipating a material requirement or need through purchasing's involvement on a new-product development team different from reacting to a purchase need?

Suggest some possible strategic initiatives that Sigma could pursue to continue its growth

Was there some other way to estimate the cost of equity as a check on the CAPM calculation?