Functions of water stops in joints of box culverts, Civil Engineering

Assignment Help:

Question
What will functions of water stops in joints of box culverts and drainage channels?

Answer
Principal function of water stops is to stop liquids, water-borne materials and solids to go through concrete joints. In essence, it plans at provided that water tightness to drainage channel.

Moreover, water stops in drainage channels or box culverts are able to also serve two reasons-
(i) To evade water contacting joints dowel bars and causing corrosion.
(ii) To evade water seeping in from underside of drainage channels or box culverts, thus washing in dirt particles and causing void under these structures and at last leading to their failure. To serve second purpose, clearly only one water stop is necessary at depth location.

To serve up first purpose, water stop has to be installed on pinnacle of dowel bars to stop water from drainage channels from leaking from side to side. On other hand, water stop has to be offered under dowel bars to keep away from secretive water from surging upwards.

In fact, other way out to serve first purpose is by using corrosion anti bars.

 


Related Discussions:- Functions of water stops in joints of box culverts

Bedding of precast concrete paving units, Q. Sand layer vs. cement sand use...

Q. Sand layer vs. cement sand used as bedding of precast concrete paving units Cement sand is a mixture of sand and cement and it behaves as a cohesive mass once mixed. Usuall

Computer programming, compare 2 numbers and print either the message identi...

compare 2 numbers and print either the message identifying the greater than number(or) the message starting that both number are equal

Slope protection, what is the type of slope protection that use rocks and p...

what is the type of slope protection that use rocks and put cements between those rocks??the concept is same as brick layer

House, how to make a home

how to make a home

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Varignon''s Theorem, What is the easiest way to give proof the varignon''s ...

What is the easiest way to give proof the varignon''s theorem? Help please guys

Levelling procedure, how to carry on leveling using dumpy level????????????...

how to carry on leveling using dumpy level????????????

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd