Foundation depth and arrangement, Civil Engineering

Foundation Depth and Arrangement:

There are two types of foundations, viz,

(a) Shallow foundations, also known as open foundations, and

(b) Deep foundations.

Slab culverts and small bridges are generally provided with shallow foundations. Even for large bridges, if good rocky strata are met with at shallow depths, open foundations are adequate. If the strata are erodible, open foundations can be protected by providing impermeable flooring protected by cut-off walls (Figure 3).

313_Foundation Depth and Arrangement.png

Figure: General Arrangement of Floor Protection Works

Deep foundations are generally made of wells for rivers. For land structures, pile foundations are adopted. For erodible beds (such as alluvial streams), the foundations should be taken to a depth below the maximum high flood level equal to 1.33 times the maximum scour depth. The scour depth is calculated from the Lacey's formula:

D = 0.473 Q 1/3/f1/ 3

where D = Scour depth in m,

Q = Discharge in cu m per sec, and

f = silt factor, equal to 1.76 √m, where m is the mean diameter of the particles in mm.

Posted Date: 1/22/2013 6:49:49 AM | Location : United States







Related Discussions:- Foundation depth and arrangement, Assignment Help, Ask Question on Foundation depth and arrangement, Get Answer, Expert's Help, Foundation depth and arrangement Discussions

Write discussion on Foundation depth and arrangement
Your posts are moderated
Related Questions
What is Initial Prestress From the transfer stage, tensile stresses in tendons apply compressive stresses in concrete. The initial value of  these stresses (in tendons or in co

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

A contractor will place 90-cubic yards of concrete for a housekeeping pad on the rooftop of a 36-ft tall building. Site conditions dictate that the safest and best method of placem

why strength of transition zone is less than bulk paste

LA values of different sizes of materials can be proportionately determined?

finding the mean ,mode and mediam

Q. Write short notes on the following : a) Points to be kept in mind while collecting water samples for testing from tap, stream & T/well separately. b) Where and why foot

sieve analsis full asignment

Determine elongation because of self weight of bar:

Two load tests were performed at a site-one with a 50 cm square plate and the other with a 75 cm square plate. For a settlement of 15 mm, the loads were recorded as 50 kN and 90 kN