Forecasting system outputs, Mechanical Engineering

Forecasting System Outputs:

In a company, inventory level is reviewed biweekly. If the parts used in an assembly have the lead time of one and a half week, what period should a forecast of requirements of parts cover for replenishment?

Solution

Forecast period = lead time + review period

= 1.5 weeks + 2 weeks

= 3.5 weeks

However, the replenishment of parts needs a forecast of requirements at least 3.5 weeks into the future.

Posted Date: 1/31/2013 6:30:57 AM | Location : United States







Related Discussions:- Forecasting system outputs, Assignment Help, Ask Question on Forecasting system outputs, Get Answer, Expert's Help, Forecasting system outputs Discussions

Write discussion on Forecasting system outputs
Your posts are moderated
Related Questions
A new high temperature alloy has been developed with creep properties as follows: stress exponent, m = 4.5, activation energy, Q = 110,000 J/mol and pre-exponential constant,


Use of hartung governor

Resultant of Non coplanar concurrent force system: How do you find resultant of Non coplanar concurrent force system? Sol.: The resultant of non concurrent force system

Q. Process of Corrosion in BFW Tank? The feed to the BFW Tank is hot and will be flashing when it enters the tank. The vapours will be corrosive when the tank is open to atmosp

Product Data Exchange Specifications (PDES) By 1984, many of these international efforts had produced enough results to be compared, and an international community was preparin

Screw Driver: Screwdrivers of different sizes are used to tighten or loosen screws. These are made of vanadium steels. A typical screw driver is shown in Figure. Fig

The Power Method is a classic numerical algorithm for determining the largest eigenvalue and eigenvector associated with a matrix A. Write a matlab function that returns the larges

Explain the construction and principles of operations of induction motor

Cross Belt Drive: When shafts are rotating in the opposite direction, cross belt drive can be obtained. Figure In the diagram given to us pulley 'A' is called as