Flexibility in contracts, Other Management

Flexibility in contracts

In the "1? and "2? modes, the single entity is the Lump Sum Turnkey Contract (LSTK), EPC contractor and the D-B contractor respectively. In both these modes, the contractor acts as a single point responsibility for the implementation of the project i.e. the contractor accepts financial liability for failure to meet any of the salient project deliverables of schedule, cost and performance. The drawback in this model is that you cannot change design or introduce new scope.

Mode "3? allows a good deal of flexibility to you, i.e. you will be able to maintain both executive control and open options for as long as possible, to respond to external conditions in this mode.

Theoretically, in mode "3?, the single entity model can be achieved if you can designate a project manager for in house project planning and project engineering personnel can report for the duration of the project.

In such a case, this team should have certain features which set it apart from the traditional function of a project company. For example:

  • A centralised clearing system should be established for timely project decisions involving diverse interests.
  • The team should get directly involved in managing participation by parties normally outside its direct control. The team should handle diverse activities such as feasibility studies, changing requirements, regulatory requirements, so on all of which are time-phased, and which require coordinated planning, scheduling, and control.
  • Organisational conflicts are bound to occur which need to be dealt with by top management.
  • The project staff hired will have to get back to their original function as you may not hire them in near future.

Construction projects are one-time undertakings and they do not justify for you to set up an in house staff, both from the viewpoint of efficient utilisation of staff and lack of project management skills. Hence, for medium size and big size projects, the project manager and the project team should be an outside agency and you can nominate a representative to whom the outside agency?s project manager reports. The benefits provided by the outside agency are that the agency?s services are more flexible; the agency usually has access to varied resources, and costs little in comparison to the total project commitment throughout its life.

This outside agency is popularly known as Project Management Company (PMC). You award the contracts for supplies and construction while the entire coordination and interfacing of the project works are carried out by the PMC.

In summary, you have understood that the degree of flexibility owned by you is greater in the D-B-B mode of contracting compared with the LSTK EPC mode of contracting. Some flexibility for changes can also be incorporated in the LSTK EPC mode, for example, escalation formula for providing financial compensation to contractor, mutually agreed basis for computing compensation for  marginal  extra  works  i.e.  works  not  envisaged  in  the original contract. Generally, a LSTK contractor will be inclined to demand a higher compensation and grant of longer time extensions for project completion when faced with major extra works.

The degree of flexibility in the D-B mode would fall between that of D-B-B mode and LSTK mode.

Posted Date: 9/28/2012 2:18:33 AM | Location : United States







Related Discussions:- Flexibility in contracts, Assignment Help, Ask Question on Flexibility in contracts, Get Answer, Expert's Help, Flexibility in contracts Discussions

Write discussion on Flexibility in contracts
Your posts are moderated
Related Questions
Product development cycle   All products under development typically follow the cycle of market place-to-market place. The development starts with identification of a product in

T ools and techniques used for quality assurance All the tools used for quality planning and quality control are used for quality assurance as well. In addition to these tools

Question 1: Explain the important steps involved in assessing talent management process. Describe Talent management process steps involved in assessing talent manageme

P roject Approaches for Capability Development The project team must understand the difference between quality assurance and control. Both are the essential elements of qualit

Problem QC is often performed by a team of professionals who use specific techniques. These techniques do vary depending on the intended measurement. Without QC techniques, a c

Pigeon hole type in Periodical Display Rack-library furnitur in library management it has two parts, one is a cupboard in the bootom and the other pigeon holes at the to,-Over


Question: (a) What do you understand by the term ‘An Organization'? (b) Differentiate between ‘A Formal Organization' and ‘An Informal Organization' (c) List three fac

Reference Service:  Notwithstanding library catalogues and various other aids available for exploiting the library resources, users would frequently need some personal assista

a) Explain why the following security measures are important in e-banking: (i) Data confidentiality (ii) Data Integrity (iii) Access control (iv) Auditing b)