Feedback mechanism - element of total quality management, Project Management

The customer feedback and employee feedback mechanisms are the essential requirements to create customer oriented quality culture. These feedback mechanisms perspectives an accurate evaluation of the operations of the company from bot internal and external perspectives. This evaluation indicates how the operations affect internal and external customers and provide a measurement of customer satisfaction. The information can be gathered through questionnaire surveys interviews use of focus groups and field complaints suggestion systems etc.

Posted Date: 3/1/2013 4:32:20 AM | Location : United States







Related Discussions:- Feedback mechanism - element of total quality management, Assignment Help, Ask Question on Feedback mechanism - element of total quality management, Get Answer, Expert's Help, Feedback mechanism - element of total quality management Discussions

Write discussion on Feedback mechanism - element of total quality management
Your posts are moderated
Related Questions
Q. How do I organize and apply resources? A. The first moreover most important step in the implementation phase is to re-visit the project plan (or the project brief) and to

T Company has identified a need for, and made a decision to open, a new training centre in one of the major cities in E Country. This is a large scale project for T Company and it

Question 1: (a) How does Training differ from Development? (b) Elaborate on the different training methods, highlighting their relative advantages and disadvantages. Ques

QUESTION (a) Accurate estimation is crucial for effective planning and control and is associated with time, information, experience of estimator, techniques used and funding. D

Principles of Success for the Project Manager Project  managers  always  hire  the  best  people  available  and  then  do whatever it takes to keep the project up and running.

can make two project for me?

Greater Possibility of Space Utilization There will be a greater productive utilization of the floor area under this type of layout. Due to lesser need for temporary storage o

Line Balancing Procedure in Assembly Layout step1: Determine what tasks must be performed to complete one unit of a finished product and the sequence in which the tasks mus

Please note that the exam is an individual effort (NOT a group effort). Please be sure that all the submitted work is your own. You cannot discuss the test with your classmates or

Identify the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -