Family Planning, Project Management

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?

Posted Date: 10/21/2012 2:17:02 PM | Location : United States







Related Discussions:- Family Planning, Assignment Help, Ask Question on Family Planning, Get Answer, Expert's Help, Family Planning Discussions

Write discussion on Family Planning
Your posts are moderated
Related Questions
Explain the project scheduling in project management software. Project scheduling: Project software can assist automatically generate Gantt charts or critical path diagra

Scenario Even ‘well run' organisations can fail to stay atop of their industries when they are challenged by certain market or technology change. Change is an imminent part of busi

Project stages A project may consist of one or more stages depending on the size of the project, its nature and client needs. Each stage has several tasks.  Possible stages

Improving the quality of manufactured parts and decreasing the production cycle time requires the use of high powered software programs integrated with computer controlle


Question: A brilliant UTM student at the end of his graduation is in presence of two opportunities and has to choose between them. One is a job offer with a salary of Rs15,000

2JN is a large manufacturing organisation which is structured with a number of supervisors every responsible for their own work production unit. Supervisors report to a team of sen

Change Management Plan for an Organisation Explain: (i) Background to organization (one page max) (ii) Analyse the organization situation by conducting a force field anal

H i stograms Histograms show a visual summary of the data, which is simple to understand. Raw data is difficult to understand and a pictorial representation helps to understa

Perform a status assessment of the second Elaboration iteration. DO NOT GENERALISE. Assess each activity separately against the outcomes specified for the activity. Generate a deta