Family Planning, Project Management

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?

Posted Date: 10/21/2012 2:17:02 PM | Location : United States







Related Discussions:- Family Planning, Assignment Help, Ask Question on Family Planning, Get Answer, Expert's Help, Family Planning Discussions

Write discussion on Family Planning
Your posts are moderated
Related Questions
H i stograms are of five types. They are: B ell shaped: It can be applied for concepts such as average and standard deviation. D ouble peaked: It is used to com

What are the contents of post completion report? Contents of a PC (post completion) report: a. Outcomes documented through staff appraisals undertaken b. Stakeholder surv

Components of Quality 1. Product feature shave a major effect on sales income ( through market share premium prices etc) . in many industries the total external cust

How is Economic Order Quantity depended on costs? Economic Order Quantity depends on two costs as illustrated below: - Inventory procurement costs that consist of expenditur

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac



QUESTION Implementation should focus on the achievement of agreed outcomes, so that if a problem is encountered with the plan, other courses of action will be employed. Wha

Perform a status assessment of the first project iteration (IIP1). DO NOT GENERALISE. Assess each activity separately and specifically against the intended outcome stated in the it

Feasibility Analysis Market analysis Competition: To protect the community against harmful needle injuries Yarra council has already implemented the syringe manageme