Family Planning, Project Management

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?

Posted Date: 10/21/2012 2:17:02 PM | Location : United States







Related Discussions:- Family Planning, Assignment Help, Ask Question on Family Planning, Get Answer, Expert's Help, Family Planning Discussions

Write discussion on Family Planning
Your posts are moderated
Related Questions
Question: (a) Any project has a beginning and an end; without a formal closure process, project teams can fail to recognize the end and this can drag the project into unnecessa

Prepare a 1-page Cost Estimate in MS Excel for the project similar to the example provided below. Use the WBS items provided below, and be sure to document assumptions you make in

The customer feedback and employee feedback mechanisms are the essential requirements to create customer oriented quality culture. These feedback mechanisms perspectives an ac

Step 1 Advise the instructor in writing if you will be working on the project individually or with another class member(s). Choose your team member (s),carefully, as you will have

Develop a work breakdown structure (WBS) for the project based on the Summary of Project Deliverables in the scope statement. Recall that a WBS is a set of deliverable-oriented gro

VK Ltd a multi-product Company, furnishes you the following data relating to the year 2000. First Half of the year Second Half of the year Sales Rs. 45,000 Rs. 50,000 Total Cost Rs

Internal and external factors influence the organisational culture Culture facilitates internal integration and harmony as well as external adaptation according to environmental

A reas of Business Excellence Typically, we think about business excellence in the terms of superiority, but in practice, it is frequently translated into features of the busi

what are the limitations of financial management and control in tertiary institutions

What is the best way to learn ITTOS?