Family Planning, Project Management

Dr. Adinombe Watage, deputy director of the Family Planning Research Center in Nigeria’s Over-the-River Province, was assigned the task of organizing an training five teams of field workers to perform educational and outreach activites as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers, and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accomodations for the participants.
Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequence, and the time that they would require. Their results are displayed in Table 1.
Louis Odaga, the chief clerk, noted that the project had to be completed in 60 days. Whipping out his solar-powered calculator, he added up the time needed. It came to 94 days. “An impossible task, then”, he noted. “No,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 10 of us in this office.”
“I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given in Table 2.
Discussion Questions
1. Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required networks of tasks and define the ciritical path. What is the length of the project without crashing?
2. At this point, can the project be done given the personnel constraint of 10 persons?
3. If the critical path is longer than 60 days, what is the least amount that Dr. Watage can spend and still achieve this schedule objective? How can he prove to Pathminder Foundation that this is the minimum-cast alternative?

Posted Date: 10/21/2012 2:17:02 PM | Location : United States







Related Discussions:- Family Planning, Assignment Help, Ask Question on Family Planning, Get Answer, Expert's Help, Family Planning Discussions

Write discussion on Family Planning
Your posts are moderated
Related Questions
There are also seven decide modules on our model. The first one decides whether patients need a wheel chair or not; if yes, they will be sent to a clerk who is responsible for spec

How are the technical skills required for a successful manager? Technical skill consider to the proficiency in handling processes, methods and techniques of an exact kind of in

Question 1: (i) What are the various aspects you would consider while planning to build a new international airport? (ii) With relevant arguments discuss the necessity or

Carry out a literature search and write a short report on 'The Human Aspects of Project Management and its Influence on Project Performance'.  Report should be no more than 5 pages

The individual is a central feature of organisational behavior and a necessary part of any behavioral situation. According to the study findings, that organisational value has help

You are an accountant who has been approached by two people, Bill and Steve, for some advice.  Bill and Steve are planning to open a furniture store in Toronto.  They plan to rent

Q. Can surprises be reduced? Yes absolutely! By their vary nature projects are uncertain business and uncertainty can lead to both risk and opportunities. As a result a very im

Risk Breakdown Structure for a Project  Risk Breakdown Structure (RBS) is a hierarchical list of risks, which standardises the department's personnel resources that help in pla

What are the disadvantages of top-down centralised approaches? The disadvantages top-down centralised approaches: Project budgets can be imposed by using top-down which is c

Explain about the project management systems. Project management systems: Each project must have a plan and a set of goals or performance measures to achieve this. Contro