Explain what is the critical path, Operation Management

Shirley Hopkins is developing a problem in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activities Immediate Predeccesor(s) Time (days)

A -- 2
B -- 5
C -- 1
D B 10
E A,D 3
F C 6
G E,F 8

a) Develop an AON network for this problem.

b) What is the critical path?

c)What is the total project completion time?

d)What is the slack time for each individual activities?

Posted Date: 2/11/2014 4:50:19 AM | Location : United States







Related Discussions:- Explain what is the critical path, Assignment Help, Ask Question on Explain what is the critical path, Get Answer, Expert's Help, Explain what is the critical path Discussions

Write discussion on Explain what is the critical path
Your posts are moderated
Related Questions

You are to write a paper analyzing an ethical issue (of your choice) in business. You are to identify the key ethical issues and argue a particular ethical position. In your argume

You are the Stores Manager at the Ministry of Information and you have the responsibility of managing store room No. 101 where all blank papers for this Ministry are kept. The ann

Risk is often described as the event that "might" happen during the course of a project. Explain how risk has impacted a project that you have been associated with as a team member

Evaluation of potential projects by weighted scoring matrix: A five year project has a projected net cash flow of $20,000, $25,000, $35,000, $15,000, and $25,000 in the next f

Exactly how should "sustainability" be best defined when making it part of a gold statement or performance objective for a business or organization?

Document three types of cost and determine which is the most difficult to control. Support your response and identify a method(s) that would enable you to overcome the difficulty.

It is Monday 3rd of June and Sarah is delighted that at the end of last week her staff managed to finish all the outstanding jobs. Sarah is in charge of a proofreading department a

SUMIT Products Ltd. is a company that produces and markets steel cups, teaspoons, knives and forks for the catering industry. The company was established in 1958 in response to the

Freight car loadings over a 12-year period at a busy port are as follows: Week Number Week Number Week Number 1 220 7 350 13 499 2 245 8 360 14 475 3 284 9 423 15 526 4 275 10 380