Explain gear box sub-assembly, Operation Management

Assignment Help:

Production and management Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?


Related Discussions:- Explain gear box sub-assembly

Explain why are company/organizational politics important, Why are company/...

Why are company/organizational politics important to a manager?

Explain the different approaches to globalization strategies, 1) How does c...

1) How does corporate strategy differ from business strategy? Give me an example of each. 2) What are the "ups and downs" of a growth strategy? 3) Discuss the different appro

Explain large regional hospital systems and research, Case Scenario: Hearts...

Case Scenario: Heartsong LLC. Heartsong LLC is a designer and manufacturer of replacement heart valves based in Peoria, Illinois. While a relatively small company in the medical de

Define what behavioural predictions might you make, What behavioural predic...

What behavioural predictions might you make if you know that an employee had an external locus of control? If an employee had a high need for achievement? If an employee had a low

Explain the essence of project management is risk management, Consider the ...

Consider the following statement: "The essence of project management is risk management." What does it mean in terms of completing a project successfully? Support your response wit

Compute the movement cost or load, Registration at Southern University has ...

Registration at Southern University has always been a time of emotions, commotions and lines. Students must move among 4 stations to complete the process. Last semester's registrat

Explain what are the problems that walmart has faced, What are the problems...

What are the problems that Walmart has faced and what has the company done to address

Explain the way of clear communication, On a recent trip to India, Mr. Yang...

On a recent trip to India, Mr. Yang, a prominent Chinese executive, dined with his client Himanshu Jain. Mr. Yang commented that the food was spicy, which Mr. Jain interpreted as a

Describe presence of an outside threat correlates, Some people argue that t...

Some people argue that the presence of an outside threat correlates with high degree of team cohesion. Would you agree or disagree?

Explain humidity can be controlled, Company A uses an unstable chemical com...

Company A uses an unstable chemical compound that must be kept in an environment where both temperature and humidity can be controlled. Company A uses 800 pounds per month of the c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd