Estimate the probability - noncritical path , Mathematics

An advertising project manager developed the network diagram shown below for a new advertising campagign.  In addition, the manager gathered the time information for each activity, as shown in the below table. 

Estimate the probability that the noncritical path B-F-G will take more than 20 weeks.  Hint:  Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.

Activity                Optimistic           Most likely         Pessimistic         Immediate Predecessor(s)

A                               1                              4                              7                              -

B                                2                              6                              7                              -

C                                3                              3                              6                              B

D                                6                             13                           14                           A

E                               3                              6                              12                           A,C

F                               6                              8                              16                          B

G                               1                              5                              6                           E,F

Posted Date: 3/19/2013 6:34:19 AM | Location : United States







Related Discussions:- Estimate the probability - noncritical path , Assignment Help, Ask Question on Estimate the probability - noncritical path , Get Answer, Expert's Help, Estimate the probability - noncritical path Discussions

Write discussion on Estimate the probability - noncritical path
Your posts are moderated
Related Questions
who created math?

The distribution of sample means is not always a normal distribution. Under what circumstances is the distribution of sample means not normal?


(a) Derive the Marshalian demand functions and the indirect utility function for the following utility function: u(x1, x2, x3) = x1 1/6 x2 1/6 x3 1/6    x1≥ 0, x2≥0,x3≥ 0


the ratio of dogs to cats is 2 to 9.if there are 10 dogs how many cats are there?

the limit of f(x) as x approaches 5 is equal to 7. write the definition of limit as it applies to f at this point

E1) Try and see the order in which different children fills numbers in the grid above. My claim is that all of them would fill in the ones, the fives and the tens first. Test my hy


examination questions and answers to the above title.