Estimate the net present worth - construction management, Civil Engineering

Assignment Help:

Three alternatives are being considered for improving a street intersection.The annual dollar savings on account of the improvement is shown below.  Assume that the intersection will last for 25 years and the interest rate is 5%.  Each of the three improvements is mutually exclusive but provides similar benefits. The alternative that is the most economical is: 

Alternative                         Total cost         Annual Benefit

A                                       $10,000           $  800

B                                       $12,000           1,000

C                                       $19,000           1,400

Solution:

Estimate the Net Present Worth (NPW) for each alternative and identify the most economical alternative for construction. 

Net Present Worth (NPW) = PW of benefits - PW of costs

Use the present worth factor for uniform series: 

  (P/A, i =5%, 25 yrs) = 14.094 (from the Factor Tables)

  NPW(A)  = ($800 x 14.094) - $10,000     = $1,275.20

  NPW(B)  = ($1000 x 14.094) - $12,000   = $2,094.00   

  NPW(C)  = ($1400 x 14.094) - $19,000   =   $731.60

Therefore, select Alternate B because it has the highest net present worth.


Related Discussions:- Estimate the net present worth - construction management

Mixture of phases, Phases are usually identifiable because of adifference i...

Phases are usually identifiable because of adifference in density which causes gravitational separation. e.g. Ice floats on water, steam rises.

Use plain dumb-bell type and center-bulb sort, Question While selection...

Question While selection of waterstop, shall engineers use plain dumb-bell type , center-bulb sort ? Answer Plain dumb-bell kind is used for joint site where sm

Explain the toxic characteristics - hazardous waste, Explain the Toxic Char...

Explain the Toxic Characteristics - Hazardous Waste - From the results of either  - Extraction Procedure(EP) toxicity (prior to March 1990) or Toxicity Characteristic Leachi

Soil compaction test, Question In soil compaction test , if test resul...

Question In soil compaction test , if test result exceeds 100%, should engineers accept result? Answer Soil compaction is method of increasing soil density by re

Determine the uses of full prestressing, Determine the uses of Full Prestre...

Determine the uses of Full Prestressing A prestressed concrete structural member is said to be fully prestressed if sufficient prestresses are introduced so that  tensile stres

Timber, TIMBER Timber refers to wood utilized for construction works. A...

TIMBER Timber refers to wood utilized for construction works. Actually the word timber is derived from an old English word 'Timbrian' that means 'to build'. A tree that yields

How to calculate the vertical stress, A rectangular foundation, 2 m × 4 m, ...

A rectangular foundation, 2 m × 4 m, transmits a uniform pressure of 450 kN/m 2 to the underlying soil. Verify the vertical stress at a depth of 1 metre below the foundation at a

Estimate the activity durations - construction management, Estimate the Act...

Estimate the Activity Durations The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this

Surveying, what is meant by geodetic survey

what is meant by geodetic survey

PRC, what is the bleeding of concrete?

what is the bleeding of concrete?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd