Environmental Question, Civil Engineering

An activated sludge tank treats 1 MGD from the primary clarify and has an X of
2200 ppm SS. The water euent is 0.9 MGD. 1.0 MGD of the sludge is recycled back into the tank
and has an [SS] of 3980 ppm. The concentration of the BOD exiting the primary clarier is 200
ppm.
(a) What are Qw and Xw?
(b) What are Qc and Xc?
(c) What are Q1 and X1?
(d) What is Xe? (Answer = 24.4 ppm)
(e) Calculate the volume of the tank that will satisfy the following requirements:
(e-1) BOD loading < 35 lb BOD/1000 ft3day
(e-2) Sludge age > 5 days
(e-3) Aeration period > 4 hr
Posted Date: 4/1/2013 10:52:47 PM | Location : United States







Related Discussions:- Environmental Question, Assignment Help, Ask Question on Environmental Question, Get Answer, Expert's Help, Environmental Question Discussions

Write discussion on Environmental Question
Your posts are moderated
Related Questions

Q. ACSR (Aluminium Conductor Steel Reinforced) are utilized as (A) over head transmission lines.            (B) super conductors. (C) fuse

Question For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement? Answer Becau

Q. What is Imp rest Stores? Material obtained not for specific works but as a standing advance for the purpose of material urgent requirements as and when they arise should wit

While calculating Active Earth Pressure, do Coloumb''s Theory and Rehbann''s theory yield same results? I''ve tried and didn''t get the same results. Where might be the mistake?

Break even point: EM Electricals, Inc., contains fixed costs of Rs. 600,000 this period. Variable costs involved labour charges of Rs.100 per unit and material cost of Rs. 200



A clay layer 25 metres thick has a saturated unit weight of 19.2 kN/m 2 . Ground water level occurs at a depth of 5 metres. It is proposed to construct a reinforced concrete founda

ADVANTAGE AND DISADVANTAGE OF TIMBER PILE