Engineering project control, Civil Engineering

Assignment Help:
need help with my assignment.
An Asian Pacific capital city proposes to design, construct and operate a new double track railway from the city to connect to its major airport. Prefeasibility studies that included geotechnical engineering investigations considers that ground conditions are such that the double track railway will need to be constructed both at grade or be elevated on a viaduct as detailed below for the various lengths of line:

Chainage:

0-3km - on grade
3-6km - on viaduct
6-8km - Estuary Viaduct
8-10km - on viaduct
10-15km - on grade

Construction time estimates have been prepared for Stage 1 of the project which will consist of the construction of the viaduct section of the line from 3km to 10km. (An example of a recently completed similar project is on a new high speed railway from Erfurt to Leipzig/Halle in Germany – the ‘Saale-Elster Viaduct which is 6.5km in length – reference below).

Following completion of the viaduct section a separate contract will be let for the installation of the track components where it is proposed to use prefabricated/precast concrete slab track sections (PCSTS) that will be erected in sections for each of the two tracks. For the purpose of analysis, the FFB Slab Track ‘Bogl’ system that has been used successfully in Germany and China will be considered.

It will be necessary to construct PCSTS fabrication plant/s located at a strategic point/s along the length of the viaduct section of the route. Fabrication plant/s of modular construction will take an estimated 3 months to construct and commission and be ready to produce the PCSTS sections. Work on this activity will need to start at contract commencement following a 1-month period of mobilization by the contractor.

Each modular plant should be capable of producing an estimated 75 off, PCSTS sections per day of operation. The PCSTS sections are to be stockpiled at the fabrication plant after manufacture for 2 months prior to the track laying operation on the viaduct commencing.

Sections of 60kg/m rail will arrive at the start of the viaduct section (3km point) on special flat wagon trains, to complete the track laying operation, and once installed will need to be site welded to ensure that there is continuous welded rail installed over the whole length of the route. It is assumed that on grade sections of line will have been completed and track laid.

On each side of the proposed viaduct route it will be possible to construct vehicular access tracks except for the estuary section that will be over water i.e. no roads can be built.

b1. Prepare a step-by-step, detailed methodology for how you would propose to construct the double line of track work for the length of the viaduct. Include a list of construction plant and equipment that will be needed for the operation.

Related Discussions:- Engineering project control

Engineering Science, 1(a)Explain the difference between a concurrent and a ...

1(a)Explain the difference between a concurrent and a non concurrent force system . (b)If a non coplanar force system is acted upon by equal and opposite forces,it must be in equil

Univariate normal distribution, Univariate normal distribution: Let X ...

Univariate normal distribution: Let X = (X I , X 2 , ..., X n ,) has the multivariate normal distribution (5.26) of Section 5.4. Show that Y = a X ' follows a univariate norma

#title, Explain couple. What are the characteristics of a couple?

Explain couple. What are the characteristics of a couple?

Void ratio, a soil sample is 38mm in diameter and 76mm and in its natural c...

a soil sample is 38mm in diameter and 76mm and in its natural condition weighs 168g.when dried completely in an oven weighs 13o.5g.the value of Gs is 2.73.what is the degree of sat

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Precaution of damp, i need simple ans for this question tell me precaution ...

i need simple ans for this question tell me precaution of dampness

Define sounding or sensing devices, Define Sounding or Sensing Devices? ...

Define Sounding or Sensing Devices? Sounding devices are effective in checking scour in the streambed adjacent to a bridge. Although sounding/sensing devices can be used indepe

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd