Q. Earth work in high embankments?
(a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the boundary.
(b) Borrow pits must be laid out as the Engineer directions. The pits must be rectangular. The sides of borrow pits next to the toe of bank must be sloped at one to two and else where at 1 to 1.
(c ) Where the ground is low end swampy, the outer or most distant half of the borrow pits is to be excavated first.
(d) In banks over 3 metres high, the outer halves only of the borrow pits are to be marked out.
uses of Earth moving equipment
Q. Do you mean by Accelerated Aging? Accelerated ageing tests are conducted at elevated temperature of 100 o C to know the variation in hardness, UTS and elongation at break.
Design a continuous one-way solid slab supported on beams spaced at 4.2m o.c. the width of the beam is 300mm, leaving clear slab spans of 3.9. The slab carries a uniform DL= 6 KPa.
Do we take the whole length (including the over hanging portion when we say the "whole span" of th beam ?
How a water bound macadam road is maintained
types of arches
explain it
Topographical Survey and Preparation of Drawings: Topographical Survey for a road project consists of three sequential stages: (a) Reconnaissance Survey, including a study
what are the characteristics of the beam to column connection?
Define layout
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd