Draw the network diagram, Finance Basics

Draw the network diagram of the following project according to the activity list and relationships mentioned below

Table 1

Activity

Duration

Dependence

Relationships

Lag

A

2

-

-

-

B

3

A

SS

2

C

5

B

FS

4

D

6

A

E

FS

FS

5

3

E

7

A

FS

2

F

6

C

FS

2

G

5

F

FS

0

H

4

C

D

FS

FS

0

2

I

5

H

G

FS

FS

0

3

J

7

K

FS

5

K

4

I

FS

4

 

Posted Date: 7/23/2012 9:51:41 PM | Location : United States







Related Discussions:- Draw the network diagram, Assignment Help, Ask Question on Draw the network diagram, Get Answer, Expert's Help, Draw the network diagram Discussions

Write discussion on Draw the network diagram
Your posts are moderated
Related Questions
Illustrate in brief about the Investment  Process A  typical  investment  decision  undergoes  a  five  step  procedure which, in turn, forms the foundation of investment pr

Uncertainty and Safety Stocks Usually requirements may not be certain and thus the firm holds safety stock to safeguard stock out cases.The safety stock guards against delays

ROA - Return on Assets The Average of the industry ROA was 10.02% for 2004, 6.81% for 2005, and 7.32% for 2006. The chart showed that Lenovo had a little bit higher ROA th

Actions of Shareholders in Agency Conflict a) Disposal of assets required like collateral for the debt in this. In this case the bondholder is exposed to more risk becaus

1. Using the variance-covariance matrix (∑) and the expected return vector (er) given in the appendix, calculate the set of weights that correspond to the portfolio that maximizes

Debenture Finance A type of long term debt raised after a company sells debenture certificates to the holder and raises finance in return. The term debenture has its source fr

A firm's current ratio is 1.5, and its quick ratio is 1.0. If its current liabilities are $10,000, what are its inventories?   a Current Ratio

Growth Rates Most Recent Fiscal Year Fiscal Year (-1) Fiscal Year (-2) Fiscal Year (-3) Annu

The construction of a highway is broken into 14 activities as shown in the following table. Draw a bar chart of this construction project. Activity ID Desc

Hatch System - Stock Exchange This is an automatic system based on the assumption such when investors sell at a certain percent age below the top of the market and buys at a s