Draw a network for the project adn determine the critical pa, Operation Research

a)Draw a network for the project.
b)Determine the critical path.
Activity Duration Activity Duration
1-2 15 5-10 22
1-3 13 6-9 33
1-4 14 6-11 25
2-5 9 7-10 10
2-7 8 8-9 5
3-5 7 8-12 17
3-6 8 9-10 17
3-8 34 9-11 13
4-6 9 10-12 19
4-7 21 11-12 18
Posted Date: 2/16/2013 4:38:12 AM | Location :







Related Discussions:- Draw a network for the project adn determine the critical pa, Assignment Help, Ask Question on Draw a network for the project adn determine the critical pa, Get Answer, Expert's Help, Draw a network for the project adn determine the critical pa Discussions

Write discussion on Draw a network for the project adn determine the critical pa
Your posts are moderated
Related Questions
Question 1 Discuss the impact of Henry Fayol's principles of management on the modern techniques of management with the help of suitable examples Question 2 Explain the Gary

six operators are to be assigned to the 5 jobs with the cost of assignments

classification

Cases are generally based on certain issues and problems. Diagnostic, analytical and decision making skills help in case solution. A case study or case based assessment is designed

Question A - Linear Programming is most widely used technique for large number of applications in business industry as well as in various other fields. Describe in brief the steps

describe the similarities and differences of transportation and linear programing methods

application&techniques

A paper mill prouduces two grads of paper viz., X and Y. Becouse of raw material restriction, it cannot product more then 400 tons of grade X paper and 300 tons of grade Y paper in

Find a minimum cost spanning arborescence rooted,

Davidson construction company is building a luxury lakefront home in batangas coordination of the architech an sub contractors will require a major effort to meet the 44-week (appr