Draw a network for the project adn determine the critical pa, Operation Research

a)Draw a network for the project.
b)Determine the critical path.
Activity Duration Activity Duration
1-2 15 5-10 22
1-3 13 6-9 33
1-4 14 6-11 25
2-5 9 7-10 10
2-7 8 8-9 5
3-5 7 8-12 17
3-6 8 9-10 17
3-8 34 9-11 13
4-6 9 10-12 19
4-7 21 11-12 18
Posted Date: 2/16/2013 4:38:12 AM | Location :







Related Discussions:- Draw a network for the project adn determine the critical pa, Assignment Help, Ask Question on Draw a network for the project adn determine the critical pa, Get Answer, Expert's Help, Draw a network for the project adn determine the critical pa Discussions

Write discussion on Draw a network for the project adn determine the critical pa
Your posts are moderated
Related Questions
You are the emergency manager for Cheyenne County in a western state. Cheyenne County is located mid-way between two major urban areas and has historically been a rural county. The

Merits a.It is simple  to understand  and easy  to calculate. b.It is very  useful  in the  case of data which  are of  qualitative nature  like  intelligence  honesty  be

Discuss the methodology of operation research

A paper mill produces two grades of paper viz X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper in



Question 1 Discuss the types of measurement scales used in research Question 2 Identify the various ways of selecting a random sample Question 3 Discuss five advan

MEAN DEVIATION Mean  deviation of a series is the arithmetic  average of the  deviations of various  items  from the  median  or mean  of that series. Median is preferred

This is a  procedure of determining  the potential if any for improving each  of the non basic variables in terms of the objective function. To determine  this  potential  each of