Draw a network for the project adn determine the critical pa, Operation Research

a)Draw a network for the project.
b)Determine the critical path.
Activity Duration Activity Duration
1-2 15 5-10 22
1-3 13 6-9 33
1-4 14 6-11 25
2-5 9 7-10 10
2-7 8 8-9 5
3-5 7 8-12 17
3-6 8 9-10 17
3-8 34 9-11 13
4-6 9 10-12 19
4-7 21 11-12 18
Posted Date: 2/16/2013 4:38:12 AM | Location :







Related Discussions:- Draw a network for the project adn determine the critical pa, Assignment Help, Ask Question on Draw a network for the project adn determine the critical pa, Get Answer, Expert's Help, Draw a network for the project adn determine the critical pa Discussions

Write discussion on Draw a network for the project adn determine the critical pa
Your posts are moderated
Related Questions
Graphs of Time Series A time  series  is a sequence of values  corresponding  to successive points  of time. Time  series  are  graphed  with time  on the x axis  and the  oth



what will happen when line balance doesn not exist

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Photographs and Illustrations: Photographs and illustrations are documents which provide a visual or pictorial representation of a person, place or situation which words fail

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Requirements and Characteristics of a good table In the words  of Mr. Harry Jerome a good statistical table  is a triumph of ingenuity and  technique masterpiece of economy  o

disadvantages of model in operational research

#what are the methods of OR ?