Draw a network for the project adn determine the critical pa, Operation Research

a)Draw a network for the project.
b)Determine the critical path.
Activity Duration Activity Duration
1-2 15 5-10 22
1-3 13 6-9 33
1-4 14 6-11 25
2-5 9 7-10 10
2-7 8 8-9 5
3-5 7 8-12 17
3-6 8 9-10 17
3-8 34 9-11 13
4-6 9 10-12 19
4-7 21 11-12 18
Posted Date: 2/16/2013 4:38:12 AM | Location :







Related Discussions:- Draw a network for the project adn determine the critical pa, Assignment Help, Ask Question on Draw a network for the project adn determine the critical pa, Get Answer, Expert's Help, Draw a network for the project adn determine the critical pa Discussions

Write discussion on Draw a network for the project adn determine the critical pa
Your posts are moderated
Related Questions
Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Test Statistic The next  step is compute an appropriate  test statistic which  is based on an appropriate probability distribution. It  is used to test whether the null  hypo

Do it  Everything  about  the presentation is  ready and so  are you. The only  things  left if to face the audience in a confident and positive  manner and leave a mark on

maximize z=3x1+2x2 subgect to the constraints x1+x2 x1-x2 x1,x2>_0

what will happen when line balance doesn not exist

Use Big M method to Maximize(Z)=3_(x_1 )+2_(x_2 ) Subject to 3_(x_1 )+?1.5?_(x_2 )=30 x_1+x_2=20 x_1=0 x_2=0


Ask question #Minimum 100 words what can engineer planner do in métallurgie accepted#

CONCEPT AND NEED FOR INFORMATION: We shall look at the meaning, of information as also the meaning of other related words such as data, facts, intelligence, advice, knowledge