The construction of a highway is broken into 14 activities as shown in the following table. Draw a bar chart of this construction project.

Activity ID

Description

Duration

Dependence

A

Survey & Layout

6

-----

B

Clear route

4

A

C

Excavate & grade

8

B

D

Plant & material

8

-----

E

Install drainage

5

B, A

F

Lay base-course

6

B, D

G

Lay pavement-course

5

F

H

Cut joints & cure

3

G

I

Dress shoulders

5

B

J

Make side drains

7

I

K

Construct curb

8

J

L

Paint signs on road

4

J, K

M

Signal & road signs

4

 L

N

Clean up

2

E, H, K

And then compute the total duration of the project and list the critical and non-critical activities. 

Posted Date: 7/23/2012 9:49:41 PM | Location : United States







Related Discussions:- Draw a bar chart, Assignment Help, Ask Question on Draw a bar chart, Get Answer, Expert's Help, Draw a bar chart Discussions

Write discussion on Draw a bar chart
Your posts are moderated
Related Questions
Define the term- Origination Origination offers to the work of investigation, analysis and processing of new project proposals. Origination starts before an issue is really

Define Meaning of Investment Meaning of Investment: Investment involves making of a sacrifice in the present with hope of deriving future advantages. Investment has many

State the Classification of New Issue Market New market can be categorized as: (i) A market where firms go to the public for the first time through initial public offerin

what is the ambiguity

Financial management is very important for any organization as at the end what does matter is the money. An effective financial management is of high importance for ensuring the be


At the end of the fiscal year ending June 30, 2003, Microsoft reported common equity of $64.9 billion on its balance sheet, with $49.0 billion invested in financial assets (in the

Define benefit plan for the employee participants

Turnover Ratios Turnover Ratios/efficiency/asset management ratio Turnover ratio shows the efficiency along with that the firm utilized the asset or resources at its dispos

Setting a Reorder Point - ROP  Once the order quantity has been determined, the next question to be settled is when to place the order. If an order is released and it takes th