Differences between pipe jacking and micro-tunnelling, Civil Engineering

Assignment Help:

Q. Differences between pipe jacking and micro-tunnelling?

Pipe jacking is a general scheme of installation of pipes with a tunnelling shield in front and the pipes are jacked from a jacking pit toa receiving pit. Tunnelling shield for pipe jacking can be mechanical and electrical equipment for conducting the excavation work or itcould be a manual shield for workers going inside the shield to do manual excavation. For microtunneling, it is a type of pipe jacking of small sized non-man-entry pipes that are remotely controlled. Generally there are two general kinds of micro-tunnelling machines:

(ii) Pressurised slurry

Similar to Pressurised slurry TBM, excavated material is transported from excavation face to surface suspended in aslurry. 

(iii)Auger machine

Excavated material is transported from excavation face to drive pit by a cased screw auger.


Related Discussions:- Differences between pipe jacking and micro-tunnelling

Non uniform flow in open channel, #ques5. A rectangular channel is 3 m in w...

#ques5. A rectangular channel is 3 m in width and draws water from a lake. The channel slope is 0.001 and the Manning’s n is 0.0013. What will be the discharge in the channel when

Roofs, Dimensions of trusses

Dimensions of trusses

IRC class 70R, What will be the structural weight per meter for IRC class 7...

What will be the structural weight per meter for IRC class 70r bridge

Longitudinal steel – an enhancement of shear strength, Q. Longitudinal stee...

Q. Longitudinal steel – an enhancement of shear strength ? Furthermore to shear resistance provided by shear reinforcement, shear forces in a concrete section is also resisted

Length is constructed in first phase of construction, In construction of a ...

In construction of a two-span bridge (span length = L) by using span-by-span construction, why is the length of about 1.25L bridge segment is constructed in first phase of construc

Human resource, Ask question #Minimum 100 words acceFor this discussion, lo...

Ask question #Minimum 100 words acceFor this discussion, look at a specific country of your choice. Develop two brief introductions, one for a U.S. peer, and one for a peer in anot

Torque, A shaft 9 m long is subjected to a torque 30 t-m at a point 3 m dis...

A shaft 9 m long is subjected to a torque 30 t-m at a point 3 m distant from either end. The reactive torque at the nearer end will be?

Marine facilities, define and explain various marine facilities

define and explain various marine facilities

Determine the basic concepts of prestressing, Determine the Basic Concepts...

Determine the Basic Concepts  of Prestressing In the year 1904, Freyssinet tried to introduce prestresses in concrete to resist stresses developed due to external loads. Later,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd