Develop the material requirements plan, Operating System

The following information is available for three MPS (Master Product Scheduling) items:

Product A                            An 80 unit order is to be started in Week 3.

                                          A 55 unit order is to be started in week 6.

Product B                           A 125 unit order is to be started in week 5

Product C                           A 60 unit order is to be started in week 4.

Develop the material requirements plan for the next 6 weeks for items D, E, and F.  The BOMs (Bill of Materials) are shown in the below figure (1), and the data from the inventory records are shown in table 2.  (Warning: A safety stock requirement applies to item F.  Be sure to plan a receipt for any week in which the projected on-hand inventory becomes less than the safety stock.)

 

Posted Date: 3/30/2013 7:11:36 AM | Location : United States







Related Discussions:- Develop the material requirements plan, Assignment Help, Ask Question on Develop the material requirements plan, Get Answer, Expert's Help, Develop the material requirements plan Discussions

Write discussion on Develop the material requirements plan
Your posts are moderated
Related Questions
Define properties of Distributed operating system Distributed:- This system distributes computation among several physical processors. The processors do not share memory or a

Q. What merit is there in having different time-quantum sizes on different levels of a multilevel queuing system? Answer: Processes that require more frequent servicing for ins


FIXED PARTITIONING Using fixed partitioning we are able to allocate the memory Here we are dividing the memory into a few fixed partitions.Every partition may not be of the si

Write a note on deadlocks. The proper definition of deadlock A set of processes is deadlocked if every process in the set is waiting for an event that only a proces

Some people write custom memory allocators to meet their speci?c needs. Although this is not needed for most of the applications, it is also not uncommon. The goal, of course, is t

Ask question maxmum words accepted#

problems of procedure

Consider the subsequent resource-allocation policy. Requests as well as releases for resources are allowed at any time. If a request for resources can't be satisfied because the re