Determine the progress and control status of the project, Project Management

i) Explain the project management control technique called earned value analysis and illustrate the fundamental concepts. Justify your answer.

ii) Determine the progress and control status of the project below which has been running for 10 weeks, using the technique you explained in part i)

Activity

A

B

C

D

E

F

Planned cost

4

2

1

1

0

0

Earned value

2

2

0

3

3

0

Actual cost

2

2

2

2

2

0

Posted Date: 2/25/2013 1:32:56 AM | Location : United States







Related Discussions:- Determine the progress and control status of the project, Assignment Help, Ask Question on Determine the progress and control status of the project, Get Answer, Expert's Help, Determine the progress and control status of the project Discussions

Write discussion on Determine the progress and control status of the project
Your posts are moderated
Related Questions
Q. What is a project life cycle? If a project is well prearranged it will progress logically through several phases. There are four standard stages to a typical project. The fi

What is the working of definition phase in the project management? Definition phase: After the project plan that developed into the initiation phase, has been approved, a

What are the advantages of bottom-up decentralised approaches? Project budgets can be imposed by using bottom-up that is decentralised approaches for example project manager or

Compare and Contrast the KN346 investment and the "plain vanilla" alternative.

Q. What communication do I need? Communication is possibly one of the most important functions of a project manager and yet sometimes the least understood. With no people there

how to manage the parts?

What types of errors disclosed in Trial Balance? A Trial Balance discloses the given types of errors as illustrated follows: a. An item posted two times. b. A mistake int

Market analysis Competition: To protect the community against harmful needle injuries Yarra council has already implemented the syringe management plan. Hence they are seen as a

The Integrated Management Project is not intended to be an academic research report and the markers will not normally expect inclusion of a literature review or hypothesis testing.

Precedence diagram and identify the element A task having 12 work elements and their logical relationship and time ( in Seconds ) taken is given in the table below. C