Determine the optimum cost-time schedule , Cost Accounting

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!

Posted Date: 2/18/2013 1:50:37 AM | Location : United States







Related Discussions:- Determine the optimum cost-time schedule , Assignment Help, Ask Question on Determine the optimum cost-time schedule , Get Answer, Expert's Help, Determine the optimum cost-time schedule Discussions

Write discussion on Determine the optimum cost-time schedule
Your posts are moderated
Related Questions
Conceptualizing Job Costing Start to develop an understanding of job costing by thinking about the simple illustration. Jack Castle owns an electrical constricting company, Cas

from the following particulars calculate the earning of worker . rate per hours $0.50 standard time 200 hours time taken 140 hours

Prod 400000 DM cost $3 DL 24 moh v 1.80 F 4.50 products 35000 DMP12000lb@$11/lb DM use10450lb DL38500HR 880500 v moh64150 FMOH152000

A 1- year Canadian bond with a face value of 5000 can be purchased at 4800. a) Calculate the nominal interest rate in Canada. b) If the Canadian dollar is expected to depreci

a factory operates a small canteen but its annual operation has consistently shown a loss:


Waylander Coatings Company purchased waterproofing equipment on January 6, 2013, for $320,000.The equipment was expected to have a useful life of four years, or 20,000 operating ho

Assume that you are the purchaser of the building at the end of the construction period, and you have paid the developer an amount which gives you a 7% annual return on net revenue

Activity Based Costing or ABC Absorption costing shows to be relatively straightforward way of adding overhead costs to units of production utilizing, more often than not, a v

If a company trades in a building towards a new building and does not recognize a gain or loss (because of code section 1031), will this transaction affect the cash flows statement