Determine the optimum cost-time schedule , Cost Accounting

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!

Posted Date: 2/18/2013 1:50:37 AM | Location : United States







Related Discussions:- Determine the optimum cost-time schedule , Assignment Help, Ask Question on Determine the optimum cost-time schedule , Get Answer, Expert's Help, Determine the optimum cost-time schedule Discussions

Write discussion on Determine the optimum cost-time schedule
Your posts are moderated
Related Questions
Bedovin Company manufactures office tables and chairs using the job order cost system

A Market Value Schedule (in one report),for the complex. This schedule should show the market value of the complex at the end of each year of the project.  Valuation method and oth

Sensitivity Analysis The only certain thing is that nothing is sure thing. Cost structures can be anticipated to vary over the time period. Management should vigilantly analyze

Mathematical Derivation of EOQ Let cost per order is represented via Co. it is the cost incurred every instance one order is placed. Let the economic quantity purchase ever

Go the Hershey website to learn how to make Hershey chocolate. (There is also a "print friendly" version of the chocolate making process at the end of the video.) Review the proces

Which method of measuring costs associated with production is more widely used in practice A. Normal Costing  B. Actual Costing  C. Both are used equally  D. Neither one

Budgeted direct labour cost 75000 hours @ $16 per hour Budgeted manufacturing overhead 80 000 hours @ $17.50 per hour Actual direct labour cost $997 500 Budgeted manufa


King Airlines King Airlines is one of many low-cost airlines in Europe. The managers want to expand the business and have an opportunity to purchase a second-hand plane to op

Under a contract with the provincial government, ChemLabs Inc. analyzes the chemical and bacterial composition of well water in various municipalities in the interior of British Co