Determine the optimum cost-time schedule , Cost Accounting

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!

Posted Date: 2/18/2013 1:50:37 AM | Location : United States







Related Discussions:- Determine the optimum cost-time schedule , Assignment Help, Ask Question on Determine the optimum cost-time schedule , Get Answer, Expert's Help, Determine the optimum cost-time schedule Discussions

Write discussion on Determine the optimum cost-time schedule
Your posts are moderated
Related Questions
XYZ Co. manufactures automation machinery according to customer specifications.  The company is relatively new and has grown each year.  XYZ Co. operated at about 75% of practical

Which statement best describes a sunk cost? A a cost which is irrelevant for the future B a cost which must be matched against the revenue C a cost which remains the same at all le

What depreciation method does Amazon use for property and equipment? What is the range of useful lives for buildings and for fixtures and equipment? Do these useful lives make sens

Andrew Industries is contemplating issuing a 30-year bond with a coupon rate of 7% (annual coupon payments) and a face value of $1000. Andrew believes it can get a rating of A from

The Bloomington Electric Company operates in a stable industry and therefore has predictable dividend growth of 8% per year. The most recent annual dividend was paid yesterday in t

Morrow Company applies overhead based on direct labor hours. At the beginning of the year, Morrow estimates overhead to be $620,000, machine hours to be 180,000, and direct labor h

STANDARD COSTING STANDARD COSTING is a method, which uses standards for costs and revenues for the idea of control by variance analysis. It can be used either through operation

a.         What are the major equity and/or debt securities investments? What amounts are reported in the balance sheet? How significant are those amounts to the company's overall

Integrated Ledger System An integrated account ledger system, which has a number of features that may be viewed as preferable to the interlocking ledger system. In present dec

Controllable and Non Controllable Costs Controllable costs can be influenced on the level of authority at that they are being analyzed when non-controllable costs cannot.