Determine the optimum cost-time schedule , Cost Accounting

Assignment Help:

You have just been assigned to replace the current Project Manager for a very important project.  You were provided a WBS for the project planning that had already been conducted, and it indicated that there are 10 major sub-deliverables/activities for the project (labeled A-J).  You assemble the team that had been working on the project for the past several weeks and they provide you with the expected completion time and cost for each activity, as well as the crash time and cost for each activity depicted in the chart below.

Activity

Max Crash Time

Direct Costs

Normal

Crash

Time

Cost

Time

Cost

A

0

2

$300

N/A

N/A

B

1

4

$1,000

3

$1,500

C

1

5

$1,200

4

$1,600

D

2

4

$700

2

$1,400

E

2

5

$800

3

$1,200

F

1

2

$400

1

$600

G

0

5

$1,100

N/A

N/A

H

3

5

$1,050

2

$2,000

I

1

3

$500

2

$900

J

0

2

$300

N/A

N/A

They also provide you with the predecessors for each activity:

Activity- Immediate Predecessor

A-     None

B-      A

C-      A

D-     C

E-      C

F-      D

G-     B

H-     G & F

I-      E & F

J-      H & I

The team then tells you that while the chart above depicts all the direct costs for this project, their estimate shows that the indirect costs will be $1,000 for each week from start to finish.  Thus, if the total project duration is 12 weeks, indirect costs will be $12,000.  If the total project duration is 15 weeks, the indirect costs will be $15,000.

Just then the CEO walks in and tells you that she wants a project duration analysis on her desk within 24 hours to include the following;

1. Use the information provided by the team to build an AON diagram for the project.  Then compress one time unit per move using the least cost method, reducing the schedule until you reach the network's crash point.  For each move you need to show all work, to include identification of the activity(s) crashed, the adjusted total cost, and explanation of how you choose which activities to crash.  What is the fastest time in which the project could be completed?  How much would this cost?

2. Determine the optimum cost-time schedule for the project?  What is the lowest cost that can be achieved in completing the project?  Which activities should be crashed in order to achieve the lowest cost?  What are the dangers inherent in crashing this project so that a lowest possible cost might be achieved?

3. Write a 500 page executive summary that explains your work and provides answers for the CEO.  Ensure that all work is shown so that the CEO can see how you derived your answers.  This document must be presented professionally and demonstrate first rate analysis.  The last project manager for this project was fired!


Related Discussions:- Determine the optimum cost-time schedule

Inventory systems, Find a journal article online about just-in-time invento...

Find a journal article online about just-in-time inventory systems. In the subject line of your post, include the title of the article that you read. Post a link to that article wi

EXPECTED CASH COLLECTIONS, WORKED EXAMPLES OF EXPECTED CASH COLLECTIONS PAT...

WORKED EXAMPLES OF EXPECTED CASH COLLECTIONS PATTERNS

#title.payroll procedures., describe the procedures involved in payroll lab...

describe the procedures involved in payroll labour cost accounting

Calculate the amount of gross profit, Samuel Construction Company engaged i...

Samuel Construction Company engaged in a contract to construct a building on 1 July 2011 with completion of the contract by the 30 June 2014.  The contract price amounted to a tota

Assignment, with relevant illustrations and examples, discuss the different...

with relevant illustrations and examples, discuss the different overhead costing and control method.

Cost and budget, Frame-it Ltd is a manufacturer of metal picture frames. Th...

Frame-it Ltd is a manufacturer of metal picture frames. The firm's two product lines are designate S (small frames: 12 x18 cm) and L (large frames: 20 x 25 cm). The primary raw mat

What is the original cost of the auto?, I'm having a hard time with this, c...

I'm having a hard time with this, can you please help? I know the dates are imparative also in finding the solution. Stevens purchased an auto on Jan 1, 2001. On December 31, 2003

Depreciation (to be computed) by slm method, sabonis consmetics co. purchas...

sabonis consmetics co. purchased machinery on december 31,2011, paying $50,000 down and agreeing to pay the balance in four equal installments of $40,000 payable each dec 31. an as

Advantages and disadvantages of uniform costing, Advantages and Disadvantag...

Advantages and Disadvantages of Uniform Costing Advantages 1. It enables costs to be compared simply 2. It makes it easier to computerize the accounting system of d

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd