Determine the critical path, Business Economics

S M Construction has been awarded a contract to build a new manufacturing plant just outside Cardiff. The activity on arrow table below gives data on the activities involved in the plant's construction.

The total cost in completing the project in normal time is £2 million, excluding site overheads which are £8000 per week.

Table of Activities

Activity

Normal time (weeks)

Shortest time (weeks)

Reduction costs (per week)

1-2

6

4

£7000

1-3

8

4

£8000

1-4

5

3

£3000

2-4

6

3

£5000

2-5

5

3

£4000

3-6

10

8

£15,000

4-6

8

5

£6000

5-6

6

6

-

The board of directors of the company have asked you to produce a precedence (activity on node) diagram and to determine the following:

1. The critical path using normal times, the project's total duration and the total cost of completing the project.

2. The shortest time in which the project can be completed and the associated costs.

3. The lowest cost for which the project can be completed and the corresponding time.

Posted Date: 2/18/2013 4:49:48 AM | Location : United States







Related Discussions:- Determine the critical path, Assignment Help, Ask Question on Determine the critical path, Get Answer, Expert's Help, Determine the critical path Discussions

Write discussion on Determine the critical path
Your posts are moderated
Related Questions
Numerical Exercise 11. Suppose that the Fed’s inflation target is 2 percent, potential output growth is 3.5 percent, and velocity is a function of how much the interest rate differ

Define institutions in the context of business strategy, and explain the role of institutions when considering entering a foreign market. Explain the role of culture in how these i

Define methods which can be used to monitor supplier performance. Methods to monitor supplier performance are as follows: a. Approval of designs: The organisation comments o

Explain how getting right price affected the market for promoting development. Getting prices right implies: • Abolishing price controls as well as subsides on fundamentals.

How is the installation and commissioning affects the IS project? Installation and commissioning: This stage of a project is frequently either forgotten or underestimated

What are state approaches to developing? The government supposes responsibility for economic planning to attain the best possible utilize of scarce resources. An economic plan

A. The correct duopolistic firm equilibrium o/p and price B. Equilibrium profit

Illustrate liberalise or open up trade in market for promoting development? Liberalise or open up trade implies that: • Abandoning fixed exchange rates and elimination of re

abnormal supply curve

The Basic assumption which underlay the government of international economy has been that the economies of the world would converge around a capitalist model. The details of such a