Determine the critical path, Business Economics

S M Construction has been awarded a contract to build a new manufacturing plant just outside Cardiff. The activity on arrow table below gives data on the activities involved in the plant's construction.

The total cost in completing the project in normal time is £2 million, excluding site overheads which are £8000 per week.

Table of Activities

Activity

Normal time (weeks)

Shortest time (weeks)

Reduction costs (per week)

1-2

6

4

£7000

1-3

8

4

£8000

1-4

5

3

£3000

2-4

6

3

£5000

2-5

5

3

£4000

3-6

10

8

£15,000

4-6

8

5

£6000

5-6

6

6

-

The board of directors of the company have asked you to produce a precedence (activity on node) diagram and to determine the following:

1. The critical path using normal times, the project's total duration and the total cost of completing the project.

2. The shortest time in which the project can be completed and the associated costs.

3. The lowest cost for which the project can be completed and the corresponding time.

Posted Date: 2/18/2013 4:49:48 AM | Location : United States







Related Discussions:- Determine the critical path, Assignment Help, Ask Question on Determine the critical path, Get Answer, Expert's Help, Determine the critical path Discussions

Write discussion on Determine the critical path
Your posts are moderated
Related Questions
Define the process of setting objectives. What might be objectives for a newly appointed junior programmer? A hierarchy of objectives cascades down through the overall intend o


A1. Given the following production function Level of fertilizer Level of maize 0 0 1 44.9 2 83.6 3 110.1 4 127.3 5 136.9 6 139.9 7 137.1 8 129.2 a) Calculate the APP, MPP and elas

Assume Mr. Robinson deposits pounds 600 in currency at a bank. Later that day Ms. Volker borrows pounds 1200 from the similar bank. The money supply will have enhanced by pounds 60

Development Strategies are explained as follows: Keeping the reasons for the persistent poverty in the LICs aside, there are three broad progress strategies which have been ado


Assess the impact of fiscal and monetory policy on business organisations and their activities

Explain why Caerphilly are considering this model of service provision Examine the costs and benefits of joining the shared service model. Your answer should cons

What does Rostow predict? For Rostow: • Savings and capital accumulation (formation) are central to the procedure of growth therefore development • The solution to de

what are the two economy of money?