Common ways to present the project schedule include all except:
a. Gantt charts
b. Milestone charts
c. PERT charts
D. Project Network Diagrams with dates added
Solution: A PERT chart represents task dependencies but does not represent activity durations or dates.
Discuss about the post-tensioning systems In most of post-tensioning systems, when the cable is tensioned and the jack is released to transfer prestress to concrete, the fricti
Question-What are three key types of r einforcement used in pre stressing ? Answer- (i) Spalling reinforcement - Spalling stresses are established behind loaded
Q. Evaluate dimensions of apron according to Spring and Gales? Dimensions of apron according to Spring and Gales. Gales and Sethi favoured uniform thickness of laid apron while
procedure on conducting curves in field
Q. Kicker of reinforced concrete cantilever retaining walls located at the position of largest moment and shear force - why? Generally for reinforced concrete cantilever retai
Q. Avoidance of designing acute angle of concrete pavement The stress persuaded in acute angle corners of concrete pavement is far much higher than right-angle corners of the
Explain me about obstacles in chain surveying and what is meant by cross staff,offsets?
Temporary bench marks
# ???? ..
Construction of Passenger Terminal Building: There are various concepts in planning and constructing passenger terminal buildings. These are : (a) The international
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd